Site start · Co. Dublin
Ballsbridge, Dublin
Site start 5 Nov 2024
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 12 Jul 2026. The details below are as they were then. The council's register has the current status.
Search the Dublin City planning registerCurrent planning applications in Ballsbridge
What and where
PROTECTED STRUCTURE
PROTECTED STRUCTURE: the proposed development will consist of the relocation of players' changing rooms and facilities from the existing Anglesea stand to the south stand, also known as the Grandstand. The proposal will comprise partial removal and replacement of the stand scaffold to allow for the insertion and construction of a single-storey structure (gross floor area 439sq.m) to accommodate home and away players' facilities, media, medical and official's facilities, ancillary plant and storage accommodation, a vomitory to access the pitch; and all associated site development works including drainage and other site services. Royal Dublin Society complex is listed as a protected structure (record of protected structure (RPS) Ref. No. 5085) however the south stand (Grandstand) is not specified in the reference. The RPS states that the remaining structures (not listed) in the complex are excluded from the RPS and are deemed not to have protected status.
- Location
- Ballsbridge, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3307/24
- Agent
- Elliott Building & Civil Engineering Ltd
- Builder
- Elliott Building & Civil Engineering Ltd
Key facts
- Floor area
- 439 m²
- Indicative value
- €250k–500kPlanningBrief estimate
- Project type
- Protected structure
- Site start
- 5 Nov 2024
- Protected structure
- Yes
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3307/24.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 5 Nov 2024Work started · Construction of a new players facilities building and services building, which is...
- Completion certificate recordedRecorded in Nov 2024The month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Last checked 15 Sep 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area