Planning application · Co. Dublin
162-164a (inclusive) Capel Street and 33-36 (inclusive) Strand Street Little, Dublin 7
Granted on appeal 6 Sep 2021 (Refused 15 Dec 2020 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 7 by email
Key facts
- Planning application 3609/20 at 162-164a (Inclusive) Capel Street and 33-36 (Inclusive) Strand Street Little, Dublin 7: Planning application.
- It was received by Dublin City Council on 22 Oct 2020.
- Status: Granted on appeal 6 Sep 2021 (Refused 15 Dec 2020 by the council).
- Permission was granted on appeal on 6 Sep 2021; the board's decision is final. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 7 · Planning applications in Co. Dublin
Council register
The council's register shows: Refused on 15 Dec 2020.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Planning application
Planning permission for development to include demolition of buildings and redevelopment of partly vacant site for hotel with ancillary bar/cafe lobby fronting Capel Street/ Strand Street Little junction and shop in 162 Capel Street. The development consists of the following:- -Demolition of 33-36 Strand Street Little (Working Men's Club) and buildings to the rear of the shop at 162 Capel Street; -Construction of a 5 to 9-storey over basement mixed use development with setbacks at 5th and 7th floor levels from the Capel Street and Little Strand Street frontages; -Internal reconfiguration of No.162 Capel Street with retail unit at ground floor and hotel accommodation on the floors above, linked into the new building at 1st and 2nd and 3rd floor levels; -Basement level accommodating staff facilities, meeting room, admin office, store, toilets, plant rooms, gym, linen store, bicycle parking and basement to shop in No. 162 Capel Street; -Ground floor accommodating hotel reception and foyer accessed from Strand Street Little; Hotel dining, kitchen, toilets; Licensed cafe/ bar lobby front Capel Street / Strand Street Little; Service yard; Shop unit in no.162 Capel Street; bin store, ESB substation, generator and switchroom accessed from side lane off Strand Street Little; -1st to 8th floors accommodating 142 no. hotel bedrooms and ancillary facilities with set back at 1st floor rear, screened plant enclosure at 5th floor recess level and 7th floor rear; -Signage and all associated site works and services.
- Location
- Dublin 7, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3609/20
Numbers and dates
- Received
- 22 Oct 2020
- Council decision
- 15 Dec 2020
- Appeal lodged
- 19 Jan 2021
- Granted on appeal
- 6 Sep 2021
Timeline
- Application received
- Refused by the council
- Appeal lodged
- Appeal decidedGrant permission with conditions
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3609/20.Search the register
- AppealGrant permission with conditions · 309215 / 6 Sep 2021View the appeal record
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Explore the area