Protected structure · Co. Dublin

62, Fitzwilliam Square North, Dublin 2

Granted 28 Nov 2019 (final grant issued 14 Jan 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 2 by email

Key facts

  • Planning application 4154/19 at 62, Fitzwilliam Square North, Dublin 2: Change of use from educational use to office use throughout.
  • It was received by Dublin City Council on 7 Oct 2019.
  • Status: Granted 28 Nov 2019 (final grant issued 14 Jan 2020).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 2 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 28 Nov 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Change of use from educational use to office use throughout

PROTECTED STRUCTURE: The development will consist of: Change of use from educational use to office use throughout. Permission is also sought for - upgrading fire and acoustic performance of existing suspended timber floors; Provision of new disabled external platform lift to rear; modification of existing bathrooms to lower ground floor; reinstatement of opening between front and rear reception rooms to the upper ground floor level and installation of new double doors and entablature; minor modifications to internal walls and openings including removal of modern partitions and doors; replacement of existing fire door in rear sash window to the first floor with traditional inward opening double doors and reinstatement of traditional cast iron balcony externally; and all ancillary works necessary to facilitate the development.

Location
Dublin 2, Co. Dublin Map
Planning reference
4154/19

Numbers and dates

Floor area
659 m²
Estimated construction value
€2.1m to €3.1mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Protected structure
Received
7 Oct 2019
Decision to grant
28 Nov 2019
Final grant
14 Jan 2020
Site start notified
13 Nov 2020
Protected structure
Yes

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Conservation work to a protected structureNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 4154/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 13 Nov 2020Notice filed · Change of use from educational use to office use throughout; upgrading fire and acoustic...View the site start
  2. Completion certificate recordedRecorded in Nov 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 2

Get alerts for Dublin 2Free. We email you when new applications appear.

Free email alerts

Get new Dublin 2 projects by email

New applications, decisions and site starts in Dublin 2, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options