Protected structure · Co. Dublin

Nos. 9, 10, Ardee Street corner St. Luke's Avenue, Dublin 8, D08KP9P

Granted 17 Feb 2023 (final grant issued 4 Apr 2023)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email

Key facts

  • Planning application 5457/22 at Nos. 9, 10, Ardee Street Corner St. Luke's Avenue, Dublin 8, D08KP9P: Refurbishment and change of use of No.10 Ardee Street.
  • It was received by Dublin City Council on 16 Dec 2022.
  • Status: Granted 17 Feb 2023 (final grant issued 4 Apr 2023).
  • Work was due to start on 13 Mar 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 8 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 17 Feb 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Refurbishment and change of use of No.10 Ardee Street

PROTECTED STRUCTURE: The development will consist of the refurbishment and change of use of No.10 Ardee Street (protected structure), a 3 storey over basement building from part dwelling, part office use to office use only; the construction of a part 3-storey with roof terrace and a part 4-storey extension with flat roof to the North and East of No. 10 Ardee Street to provide office accommodation and lift/stairs; the provision of a 1-storey bicycle and bin store with green roof; 12No. bicycle parking spaces and 1 No. car parking space in the courtyard along with provision of a new pedestrian entrance off St. Luke's Avenue along with all associated landscape, conservation and site development works including a new boundary wall to eastern boundary. The proposed works to No.10 Ardee Street (protected structure) include the demolition of 3-storey extension to North known as "The Annex" and 1-storey toilet structure to rear (East); the removal and strip out of other non-original partitions; the reinstatement of windows to rear at ground floor and doors and windows to basement; the adjustment of internal opes into the extension at No.9 Ardee Street at ground, first and second floors with 2no new door openings at ground and first floor level; localised repointing to façades; structural strengthening where required.

Location
Dublin 8, Co. Dublin Map
Planning reference
5457/22

Numbers and dates

Project type
Protected structure
Received
16 Dec 2022
Decision to grant
17 Feb 2023
Final grant
4 Apr 2023
Site start notified
13 Mar 2024
Protected structure
Yes

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Site history

This site's history

  1. Application 5457/22Sub05 at the same address: received 16 Oct 2026, no decision recorded yet.

    7. The developer shall comply with the following requirements of the City Archaeologist: d) Where archaeological material is shown to be… Same address

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work was due to start on 13 Mar 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Conservation work to a protected structureNamed in the application description
  • Roads and site development worksNamed in the application description
  • Basement parkingNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 5457/22.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 13 Mar 2024Notice filed · The development will consist of the refurbishment and change of use of a protected...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options