Public / civic · Co. Dublin

Northwest of the existing St. Georges National School, Off the Clonard, Co. Dublin

Granted 13 Jul 2015 (final grant issued 18 Aug 2015)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email

Key facts

  • Planning application F15A/0242 at Northwest of The Existing St. Georges National School, Off The Clonard, Co. Dublin: New School building.
  • It was received by Fingal County Council on 20 May 2015.
  • Status: Granted 13 Jul 2015 (final grant issued 18 Aug 2015).

Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 13 Jul 2015.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New School building

Permission for the construction of a new School building

Location
Off The Clonard, Co. Dublin Map
Planning reference
F15A/0242

Numbers and dates

Project type
Public / civic
Received
20 May 2015
Decision to grant
13 Jul 2015
Final grant
18 Aug 2015
Site start notified
14 Dec 2015

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference F15A/0242.Search the register

How we know this

From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 14 Dec 2015Notice filed · Permission for the construction of a new School building. The building comprises two...View the site start
  2. Partial completion certificate recordedRecorded in Dec 2015 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
  3. Full completion certificate recordedRecorded in Dec 2015 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers the work listed on the certificate; later phases can have their own. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Off The Clonard

Get alerts for Co. DublinFree. We email you when new applications appear.

Free email alerts

Get new Dublin projects by email

New applications, decisions and site starts in Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options