Planning application · Co. Dublin
The Coast, Baldoyle, Dublin 13
Granted on appeal 23 Nov 2017 (Granted 7 Jul 2017 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 13 by email
Key facts
- Planning application F16A/0412 at The Coast, Baldoyle, Dublin 13: ~550 homes.
- It was received by Fingal County Council on 20 Sep 2016.
- Status: Granted on appeal 23 Nov 2017 (Granted 7 Jul 2017 by the council).
Source: the Fingal County Council planning register, as last seen on 20 Oct 2026. Open the council's file
More planning applications in Dublin 13 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 7 Jul 2017.
Application details as we last saw them in the national register on 20 Oct 2026.
What and where
~550 homes
550 no. residential units (379 no. apartments and 171 no. houses) and a village centre comprising C.1,585sq. m. of commercial floor space laid out in 13 no. blocks (Blocks A1, A2, A3, B1, B2, B3, B4, C1, C2, C3, C4, C5 and D1) ranging in height from two storeys to six storeys as follows: Blocks A1, A2 and A3 will consist of 3 no. six storey buildings (c. 30.05m OD to roof level with an overall height of c. 33.90 OD to include lift overrun) comprising 195 no. residential units (5 no. 1-bed apartment, 162 no. 2-bed apartments, and 28 no. 3-bed apartments) at first to fifth floor level, c.1,585 sq.m. of commercial floor area at ground floor level comprising a convenience outlet (c. 493sq.m.), cafe (c. 200sq.m.), 4 no. retail units (c. 88sq.m., 99sq.m., 99 sq.m. and 90sq.m.), a crèche (c. 516sq.m.) with outdoor play area (c. 183sq.m.) and shared car park also at ground floor level with two associated communal courtyard areas at first floor level above a podium. Block B1 will consist of a four storey building over basement car park (c. 21.6m OD to roof level with an overall height of c. 25m OD to include lift overrun) comprising 82 no. residential units (3 no. 1-bed apartments, 75 no. 2-bed apartments, and 4 no. 3-bed apartments); Blocks B1 and B2 include a shared central communal courtyard area over a shared basement car park and a community room (c. 78sq.m.) in the entrance pavilion to the basement. Block B2 will consist of 3 no. three storey terraces over basement car park comprising 24 no. residential units (12 no. own door 2-bed apartments and 12 no. own door 2-bed duplex apartments). Block B3 will consist of 1 no. two storey terrace and 3 no. three storey terraces comprising 32 no. residential units (11 no. 3-bed terraced houses and 21 no. 4-bed terraced houses). Block B4 will consist of 2 no. two storey terraces and 1 no. three storey terrace comprising 25 no. residential units (16 no. 3-bed terraced houses and 9 no. 4-bed terraced houses). Block C1 will consist of 3 no. three storey terraces comprising 32 no. residential units (16 no. 2-bed own door apartments and 16 no. 2-bed own door duplex apartments). Block C2 will consist of 1 no. two storey terrace and 2 no. three storey terraces comprising 35 no. residential units (9 no. 2-bed own door apartments, 9 no. 2-bed own door duplex apartments, 10 no. 3-bed terraced houses and 7 no. 4-bed terraced houses. Block C3 will consist of 1 no. two storey terrace and 2 no. three storey terraces comprising 29 no. residential units (11 no. 3-bed houses and 18 no. 4-bed houses). Block C4 will consist of 2 no. two storey terraces and 2 no. three storey terraces comprising 47 no. residential units (5 no. 1-bed own door apartments, 2 no. 2-bed own door apartments, 5 no. 2-bed own door duplex apartments, 2 no. 3-bed own door duplex apartments, 24 no. 3-bed terraced houses and 9 no. 4-bed terraced houses). Block C5 will consist of 2 no. two storey terraces and 2 no. three storey terraces comprising 37 no. residential units (5 no. 1-bed own door apartments, 2 no. 2-bed own door apartments, 5 no. 2-bed own door duplex apartments, 2 no. 3-bed own door duplex apartments, 14 no. 3-bed terraced houses, and 9 no. 4-bed terraced houses). Block D1 will consist of 12 no. two storey 3-bed semi-detached houses. All apartments and duplex apartments have private terraces or balconies and private communal amenity areas. The proposed development will also include 896 no. residential (including visitor) car parking spaces, 62 no. commercial car parking spaces, 551 no. residential bicycle spaces and 13 no. commercial bicycle spaces; pedestrian, vehicular and bicycle access will be via the existing Longfield Road and Red Arches Road and the proposed internal road network comprising Stapolin Avenue, Ireland's Eye Avenue and smaller access roads; construction access will be via existing haul road from the Coast Road; landscaping works including Stapolin Square (c. 0.4ha) which will provide access to Clongriffin Train Station via a series of terraces, steps and slopes, a range of public open spaces including pocket parks and amenity spaces, the largest of which will be Stapolin Haggard (c. 1.57ha); public lighting; a wetland area (c. 0.4ha.) for water quality treatment associated with the proposed development; all associated ancillary facilities including 8 no. ESB substations, switch rooms, refuse storage, water storage tanks and plant; and all associated site development works including the removal of existing roads and infrastructure where required and demolition of existing temporary lift and stair enclosure and associated infrastructure to Clongriffin Train Station. The subject site of C 15.89ha comprised Growth Area 1 of the Baldoyle-Stapolin Local Area Plan 2013-2019. This application is accompanied by an Environmental Impact Statement (E.I.S.) Significant Additional Information - Revised Public Notices Lodged 22/05/2017. (Irish Examiner 19/05/2017)
- Location
- Dublin 13, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- F16A/0412
- Application type
- Permission
Numbers and dates
- Homes
- ~550estimated from the application
- Floor area
- 1,078 m²
- Estimated construction value
- €93m to €180mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Received
- 20 Sep 2016
- Council decision
- 7 Jul 2017
- Appeal lodged
- 3 Aug 2017
- Granted on appeal
- 23 Nov 2017
- Site start
- 6 Jan 2020
Timeline
- Application received
- Granted by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file F16A/0412 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 248970 / 23 Nov 2017View the appeal record
How we know this
From the Fingal County Council planning register, as last seen on 20 Oct 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 6 Jan 2020Work started · phase 1 · Construction of 34 No. dwelling houses(Block C4) at The Coast, Stapolin, Baldoyle...View the site start
- 15 Apr 2020Work started · phase 2 · Construction of 25 No. dwelling houses(Block C5)View the site start
- 4 Dec 2020Work started · phase 3 · Construction of 12no. residential dwellings - inclusive including all associated...View the site start
- 27 Aug 2021Work started · phase 4 · Construction of 18 Houses Type P (9 Units in Block B3 and 9 Units in Block B4)View the site start
- 10 Jan 2022Work started · phase 5 · Construction of 19 No. dwellings houses (Block C3)View the site start
- 26 Oct 2026Work started · phase 6 · Construction of Block C2A (Sorrell Hall), a five-storey residential block at Stapolin...View the site start
- Completion certificate recordedRecorded in Jan 2020 · 22 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
- Completion certificate recordedRecorded in Jan 2020 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
- Completion certificate recordedRecorded in Apr 2020 · 9 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.