Large residential · Co. Dublin
Cloverhill Road, Raheen, Dublin 22.
Granted 10 May 2018 (final grant issued 18 Jun 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email
Key facts
- Planning application SD17A/0397 at Cloverhill Road, Raheen, Dublin 22.: 85 homes.
- It was received by South Dublin County Council on 18 Apr 2018.
- Status: Granted 10 May 2018 (final grant issued 18 Jun 2018).
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 22 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 10 May 2018.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
85 homes
Residential development of 85 dwellings consisting of: 65 houses and 20 apartments comprised of 4 no. 2 bed, 2 storey terraced houses, 1 no. 4 bed, 2 storey semi-detached house, 17 no. 3 bed, 2 storey semi-detached houses, 43 no. 3 bed, 2 storey townhouses in 10 terrace blocks, 1 no. 4 storey apartment block accommodating 12 no. 2 bedroom apartments and 1 no. 2 storey apartment block accommodating 8 no. 2 bedroom apartments, all on a site area of 2.91 ha. The proposal also provides for a single storey crèche (207.11sq.m) and all associated site development and infrastructural works, car parking, open spaces and landscaping. Proposed access to the development will be via permitted access (Ref. SD15A/0192) off Cloverhill Road.
- Location
- Dublin 22, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD17A/0397
Numbers and dates
- Homes
- 85
- Floor area
- 8,605 m²
- Estimated construction value
- €15m to €27mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 18 Apr 2018
- Decision to grant
- 10 May 2018
- Final grant
- 18 Jun 2018
- Site start notified
- 27 Jun 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD17A/0397 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 27 Jun 2019Notice filed · phase 1 · 8No Apartments in 1No 4-Storey block at 1-8 Cooleven GreenView the site start
- 27 Jun 2019Notice filed · phase 2 · 12No Apartments in 1No 4-Storey Block at 1-12 Cooleven WayView the site start
- 3 Jul 2019Notice filed · phase 3 · 63 No Two Storey DwellingsView the site start
- 2 Jun 2020Notice filed · phase 4 · Completion of partly constructed single storey CrecheView the site start
- Completion certificate recordedRecorded in Jun 2019 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jun 2019 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jul 2019 · 33 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.