Mixed use · Co. Dublin

Griffeen Avenue, Balgaddy, Lucan, Co. Dublin

Granted 8 Apr 2019

We no longer update this application, so we can't email you about it. Get new planning applications in Lucan by email

Key facts

  • Planning application SD198/0002 at Griffeen Avenue, Balgaddy, Lucan, Co. Dublin: ~74 homes.
  • It was received by South Dublin County Council on 31 Jan 2019.
  • Status: Granted 8 Apr 2019.

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Lucan · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 8 Apr 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

~74 homes

Social Housing Project of 74 units and a community facility on undeveloped lands at Griffeen Avenue, situated between Foxborough Lawn and Tor an Rí Walk consisting of: 22 3-Bedroom houses, 4 person, 2 storey; 4 3-Bedroom houses, 5 person, 2 storey; 21 3-Bedroom houses, 5 person, 2 storey; 9 1-Bedroom Ground Floor Apartments; 9 3-bedroom, Duplex units, 2 Storey (1st and 2nd Floor); 9 Apartments - 2 Bedroom, 3 Person, 3 storey; Community Facility. The works include: New access off Tor an Rí, landscaping works to boundaries and new park/play area, ancillary works to landscape housing areas, and all necessary associated ancillary works on the site and adjacent areas. All units to be minimum A2 BER rated. The housing provision includes ground floor, two/three storey units grouped in terraces. Plans and particulars of the proposed scheme will be available for inspection or purchased at a fee not exceeding the reasonable cost of making a copy for a period of four weeks from Thursday, 31st January 2019 during the public opening hours at the offices of South Dublin County Council, County Hall, Tallaght, Dublin 24. Submissions or observations in relation to the proposed development, dealing with the proper planning and sustainable development of the area in which the development would be situated, may be made as follows: online at https://consult.sdublincoco.ie up to midnight on Thursday, 14th March 2019 or written submissions not later than 5.00pm Thursday, 14th March 2019. Please address your submission to: Senior Executive Officer, Housing Department, South Dublin County Council, County Hall, Tallaght, Dublin 24 (NOTE: Please make your submission by one medium only). Only submissions received by Thursday, 14th March 2019 and addressed as set out above, will be considered. Submissions cannot be accepted in any other format or to any other postal address. Submissions and observations should state the name, address, and, where relevant, details of any organisation, community group or company etc. which you represent.

Location
Lucan, Co. Dublin Map
Planning reference
SD198/0002

Numbers and dates

Homes
~74estimated from the application
Estimated construction value
€12m to €23mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Mixed use
Received
31 Jan 2019
Granted
8 Apr 2019
Site start
11 Jan 2023

Timeline

  1. Application received
  2. Granted
  3. Site start

Documents and evidence

Check the record

  • Council planning fileThe application file SD198/0002 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 11 Jan 2023Work started · phase 1 · Construction of 69No residential units and associated site works at Griffeen Avenue...View the site start
  2. 7 Mar 2023Work started · phase 2 · Construction of new community centre and associated site works at Griffeen Avenue...View the site start
  3. Partial completion certificate recordedRecorded in Jan 2023 · 27 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
  4. Partial completion certificate recordedRecorded in Jan 2023 · 21 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
  5. Partial completion certificate recordedRecorded in Jan 2023 · 13 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Lucan

Get alerts for LucanFree. We email you when new applications appear.

Free email alerts

Get new Lucan projects by email

New applications, decisions and site starts in Lucan, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options