Protected structure · Co. Dublin
Crumlin Delivery Service Unit, 11, Saint Agnes Road, Dublin 12, D12 WK5A
Granted on appeal 15 Oct 2025 (Granted 20 May 2025 by the council)
Key facts
- Planning application WEB2260/24 at Crumlin Delivery Service Unit, 11, Saint Agnes Road, Dublin 12, D12 WK5A: Demolition of the existing 1 storey Delivery Service Unit building…
- It was received by Dublin City Council on 8 Oct 2024.
- Status: Granted on appeal 15 Oct 2025 (Granted 20 May 2025 by the council).
- Permission was granted on appeal on 15 Oct 2025; the board's decision is final. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.
Source: the Dublin City Council planning register, checked 2 Jun 2026. Search the council's register
More planning applications in Dublin 12 · Planning applications in Co. Dublin
What and where
Demolition of the existing 1 storey Delivery Service Unit building…
The site is within the Crumlin Village Architectural Conservation Area. The proposed development comprises the following: Demolition of the existing 1 storey Delivery Service Unit building and associated outbuildings on the site and removal of the existing site boundary wall along Windmill Road (c.918. 8sq.m). Construction of a 3-5 storey residential development comprising 53 no. 1 bed apartment units in a single block ranging in size from c.50.1 sq.m to c.53.1 sq.m. All apartments are provided with associated private open space balconies/ terraces. All units are intended to provide housing for independent living for older residents (60 years plus). Pedestrian access and egress to the development will be from St Agnes Road. The development also proposes c. 812sq.m of communal amenity open space as a landscaped garden at ground floor level (c.586.5 sq.m) and a landscaped terrace area at the roof of 2nd floor level (225.5 sq.m), a community room (c.93.4 sq.m), office room (c.11.5 sq.m), kitchenette (4 sq.m) and toilet (c.9 sq.m), associated secure bicycle and bin storage, relocation of existing ESB network kiosk and provision of a single ESB substation, switch room, water break tank room, hard and soft landscaping and all other associated site works and services above and below ground on an overall site area of c. 1784 sq.m.
- Location
- Dublin 12, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- WEB2260/24
Numbers and dates
- Project type
- Protected structure
- Received
- 8 Oct 2024
- Council decision
- 20 May 2025
- Appeal lodged
- 12 Jun 2025
- Granted on appeal
- 15 Oct 2025
Timeline
- Application received
- Granted by the council
- Appeal lodgedCase 322754
- Appeal decidedGrant permission with revised conditions · Case 322754
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference WEB2260/24.Search the register
- AppealGrant permission with revised conditions · 322754 / 15 Oct 2025View the appeal record
- Leave to appealLeave to appeal refused · 322770View the board case
How we know this
From the Dublin City Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Explore the area