Infrastructure · Co. Galway

Bus Éireann Bus Depot, Galway Harbour Enterprise Park New Docks, The Docks Galway City

Granted 3 Mar 2026 (final grant issued 14 Apr 2026)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560152 at Bus Éireann Bus Depot, Galway Harbour Enterprise Park New Docks, The Docks Galway City: Permission is sought by Bus Éireann.
  • The applicant is Bus Éireann. The agent is Enviroplan Consulting Ltd.
  • It was received by Galway City Council on 22 May 2025.
  • Status: Granted 3 Mar 2026 (final grant issued 14 Apr 2026).
  • Work was due to start on 23 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Galway City Council planning register, checked 2 Jun 2026. Open the council's file

Planning applications in Co. Galway

What and where

Permission is sought by Bus Éireann

Permission for development which consists of: Permission is sought by Bus Éireann at their existing Bus Depot, Galway Harbour Enterprise Park, New Docks, The Docks, Galway City (Eircode H91A304). The development will consist of the construction, installation and commissioning of: • 35 no. Electric Vehicle (EV) charge stations (i.e. 70 no. charge ports) to serve a new electrical fleet of buses, • A single storey switch room extension to the maintenance garage building (c. 13.47 m² gross floor area), • 1 no. free standing single storey modular substation unit (c. 35.71 m² gross floor area), • 31 no. 6m high additional lighting columns within the existing bus parking area, • Minor revisions to layout to include for relocation of existing bike shelter and security hut, together with associated installation of cabling/charging equipment and associated site works and services. A Natura Impact Statement (NIS) will be submitted to the planning authority with this application

Location
The Docks Galway City, Co. Galway Map
Planning reference
2560152
Applicant
Bus Éireann

Numbers and dates

Floor area
49 m²
Project type
Infrastructure
Received
22 May 2025
Decision to grant
3 Mar 2026
Final grant
14 Apr 2026
Site start notified
23 Jul 2026

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 23 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560152 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Galway City Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Site starts

Commencement notices for this permission

  1. 23 Jul 2026Notice filed · phase 1 · Single story MV room extensionView the site start
  2. 23 Jul 2026Notice filed · phase 2 · Proposed stand-alone single storey Modular Sub-Station consisting of a Low Voltage Panel...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near The Docks Galway City

Get alerts for Co. GalwayFree. We email you when new applications appear.

Free email alerts

Get new Galway projects by email

New applications, decisions and site starts in Co. Galway. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options