Infrastructure · Co. Galway

McLaughlin Building, Nun's Island/Gaol Road Nun's Island, Galway City Co. Galway

Under appeal since 5 Aug 2026 (Decision to grant 15 Jul 2026 by the council)

Get updates on this application

We'll email you if the decision is appealed and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560380 at McLaughlin Building, Nun's Island/Gaol Road Nun's Island, Galway City Co. Galway: Refurbishment and extension of the McLaughlin Building.
  • The applicant is University of Galway. The agent is Declan Brassil.
  • It was received by Galway City Council on 16 Dec 2025.
  • Status: Under appeal since 5 Aug 2026 (Decision to grant 15 Jul 2026 by the council).
  • The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Source: the Galway City Council planning register, checked 6 Aug 2026. Open the council's file

Planning applications in Co. Galway

What and where

Refurbishment and extension of the McLaughlin Building

Permission for development which consists of: The refurbishment and extension of the McLaughlin Building (a Protected Structure RPS Ref. 7406 Former Mill - NUIG) for educational use including associated academic teaching and study spaces; administrative areas; staff and student welfare facilities; café and ancillary plant and storage areas. The McLaughlin Building occupies the site of a 17th Century causeway (a Recorded Monument GA094-100033) situated on the Eglinton Canal/Gaol River (a Protected Structure RPS Ref. 8501 Rivers/Waterways) and contains a series of culverts beneath the building. The proposed works to the McLaughlin Building will include the removal of the mid- to late-20th Century roof and fifth floor level (approx. 374.1 m² gross floor area (GFA)); and the construction of two additional floors, resulting in an overall increase in height of the building from 5 storeys to 6 storeys (with maximum proposed height of 30.03 m AOD, c. 23.22m above proposed ground floor level). The proposed works will result in an increase in GFA from 2,962.17 m² to 3,962.7 m². Further interventions to the McLaughlin Building will include: • Removal of existing mid- to late 20th Century building fabric the south-west corner to be replaced with an ESB Substation and Switchroom at ground floor level overclad with perforated aluminium panels to match proposed new aluminium curtain walling with glazed openings on upper levels. • Provision of a new external stair and lift core on the north elevation. • Removal of selected areas of the late 20th Century internal steel frame and concrete slabs, provision of new foundations in selected areas, new ground floor slab build-up throughout and new structural frame to support the additional floors. • Existing 20th Century windows and doors to be replaced with new thermally broken aluminium doors and windows to match existing openings, and repair of window reveals and cills. • Creation of new entrance on the northern elevation (incorporating two original window openings); enlargement of three existing openings at ground floor level of southern elevations and alterations to two window and door openings to provide compliant door openings to the new escape stair to the northern elevation. • Removal of cement render and retention and repair of original rubble and limestone masonry walls. • Removal of mid to late 20th Century extension to the northern elevation. • Removal of non-original subdivisions and provision of new

Location
Nun's Island/gaol Road Nun's Island, Co. Galway Map
Planning reference
2560380

Numbers and dates

Floor area
374 m²
Project type
Infrastructure
Received
16 Dec 2025
Council decision
15 Jul 2026
Appeal lodged
5 Aug 2026
Protected structure
Yes, RPS 7406

Timeline

  1. Application received
  2. Decision to grant by the council
  3. Appeal lodged

Outlook

What happens next

The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Work packages named so far

  • Conservation work to a protected structureNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

Reviewed build intelligence

What the documents establish

Government document review

Educational refurbishment and extension under pending appeal. The FI document proposes changes to an existing protected building; its 374.1 m² removed roof/fifth-floor area is not housing output. The council decision and any later approved detail have not been reviewed.

1 official documents inspected · Checked 2026-09-05 · Official file index

Timber windows, curtain walling and masonry repairs

Proposed in application · McLaughlin educational refurbishment, Galway City 2560380; FI proposal

What the evidence says
The FI description proposes timber sliding-sash windows with slim glazing to replace twentieth-century windows; thermally broken aluminium doors/windows at new openings; aluminium curtain walling at the southwest corner; and removal of cement render while retaining and repairing original rubble and limestone walls.

Why it may matter — interpretation
Interpretation: identifies a coordinated conservation, glazing and building-envelope package.

What is not established
Final approved finishes, joinery manufacturer and installed materials are not established. The 374.1 m² figure concerns removed roof/fifth-floor fabric; it is not a dwelling count.

Inspect the evidence

McLaughlin Building: FI Appropriate Assessment Screening Report and NIS, with appendices · p.11
new timber sliding sash windows · Issued 2026-04-30 · Document control F2 dated 30 April 2026; body headers still show D2 dated 23 April. Embedded civil report is planning issue 2 dated 5 December 2025.; received 2026-05-01 · Checked 2026-09-05

new timber sliding sash windows

Sedum and gravel roof zones retain interception storage

Proposed in application · Roof surfaces of the refurbished McLaughlin Building; PV/plant zones treated separately

What the evidence says
The FI NIS proposes extensive sedum green roof over an interception storage mat, with gravel ballast over drainage boards where PV panels or roof equipment prevent a planted substrate. Roof runoff is routed to the culverts beneath the building; existing rainwater pipes discharging to the footpath are to be decommissioned.

Why it may matter — interpretation
Interpretation: identifies green-roof, waterproofing, rainwater and rooftop-equipment coordination.

What is not established
No selected roof-system brand, PV panel count or installed capacity is established. The December civil appendix describes storage assumptions; it is not a later approved roof schedule.

Inspect the evidence

McLaughlin Building: FI Appropriate Assessment Screening Report and NIS, with appendices · p.19
sedum blanket · Issued 2026-04-30 · Document control F2 dated 30 April 2026; body headers still show D2 dated 23 April. Embedded civil report is planning issue 2 dated 5 December 2025.; received 2026-05-01 · Checked 2026-09-05

sedum blanket

New 150 mm foul connection separates wastewater from stormwater

Proposed in application · Proposed foul drainage for this protected educational building

What the evidence says
The FI NIS proposes a completely new internal foul network and a 150 mm gravity foul sewer connecting to the existing 225 mm uPVC combined sewer at Nun’s Island Road. Wastewater is to be collected separately from stormwater; the source describes an existing annex discharge to the canal culvert that this refurbishment addresses.

Why it may matter — interpretation
Interpretation: identifies a specific pipework and connection package rather than a generic drainage flag.

What is not established
The positive feasibility described in the source does not establish a completed connection agreement or installed works. Final connection details and any subsequent conditions remain unreviewed.

Inspect the evidence

McLaughlin Building: FI Appropriate Assessment Screening Report and NIS, with appendices · p.19
150mm gravity foul sewer · Issued 2026-04-30 · Document control F2 dated 30 April 2026; body headers still show D2 dated 23 April. Embedded civil report is planning issue 2 dated 5 December 2025.; received 2026-05-01 · Checked 2026-09-05

150mm gravity foul sewer

2700 K or lower handrail lighting beside the river

Proposed in application · Preliminary external lighting concept at the McLaughlin north walkway

What the evidence says
The FI NIS specifies proposed LED spotlights integrated into a handrail 1.1 m above the north walkway, shielded from the Gaol River by a continuous solid metallic barrier. It calls for 2700 K or lower colour temperature, asymmetric distribution and sharp optical cut-off directed onto the path.

Why it may matter — interpretation
Interpretation: identifies warm-light, optics, handrail and shielding requirements.

What is not established
The text describes preliminary studies; no installed product, final luminaire schedule, procurement or current approval is established.

Inspect the evidence

McLaughlin Building: FI Appropriate Assessment Screening Report and NIS, with appendices · p.20
2700k or lower · Issued 2026-04-30 · Document control F2 dated 30 April 2026; body headers still show D2 dated 23 April. Embedded civil report is planning issue 2 dated 5 December 2025.; received 2026-05-01 · Checked 2026-09-05

2700k or lower
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 1 government-published PDFs were visually inspected. One 253-page combined PDF was accessed. Seven selected pages were visually inspected; this is not a complete review of its appended reports or the council case file. Proposals do not establish procurement or installed work.

How we know this

From the Galway City Council planning register, checked 6 Aug 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Nun's Island/gaol Road Nun's Island

Get alerts for Co. GalwayFree. We email you when new applications appear.

Free email alerts

Get new Galway projects by email

New applications, decisions and site starts in Co. Galway. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options