Large residential · Co. Kerry
Cahereen west, killarney raod, castleisland, Co. Kerry
Granted on appeal 8 Apr 2022 (Decision to grant 26 Jul 2021 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Castleisland by email
Key facts
- Planning application 201198 at Cahereen West, Killarney Raod, Castleisland, Co. Kerry: 67 homes.
- It was received by Kerry County Council on 9 Dec 2020.
- Status: Granted on appeal 8 Apr 2022 (Decision to grant 26 Jul 2021 by the council).
Source: the Kerry County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Castleisland · Planning applications in Co. Kerry
Council register
The council's register shows: Decision to grant on 26 Jul 2021.
Search the Kerry planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
67 homes
A) THE DEMOLITION OF AN EXISTING DISUSED SINGLE STOREY FUNERAL HOME, B) THE CONSTRUCTION OF RESIDENTIAL DEVELOPMENT OF 67 NO DWELLING UNITS CONSISTING OF 8 NO. 1 BED APARTMENTS, 12 NO. 2 BED MID-TERRACED DWELLINGS, 36 NO. 3 BED SEMI-DETACHED/TERRACED DWELLINGS AND 11 NO 3 BED END OF TERRACE DWELLINGS C) ASSOCIATED SECURE BICYCLE PARKING AND BIN STORAGE, D) VEHICULAR ACCESS TO THE PROPOSED DEVELOPMENT WILL BE VIA THE EXISTING ACCESS FROM THE KILLARNEY ROAD WHICH IT IS PROPOSED TO RETAIN, E) THE DEVELOPMENT WILL ALSO INCLUDE A PEDESTRIAN WALK ALONG THE BANK OF THE RIVER MAINE AND ALL ASSOCIATED SITE WORKS INCLUDING 134 NO. CAR PARKING SPACES, FOUL AND STORM DRAINAGE WITH ON-SITE ATTENUATION, PUBLIC LIGHTING, LANDSCAPING AND AMENITY AREAS
- Location
- Castleisland, Co. Kerry Map
- Council
- Kerry County Council
- Planning reference
- 201198
Numbers and dates
- Homes
- 67
- Project type
- Large residential
- Received
- 9 Dec 2020
- Council decision
- 26 Jul 2021
- Appeal lodged
- 12 Aug 2021
- Granted on appeal
- 8 Apr 2022
- Site start notified
- 1 Sep 2022
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 201198 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 311107 / 8 Apr 2022View the appeal record
How we know this
From the Kerry County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 1 Sep 2022Notice filed · phase 1 · Demolition of disused funeral home and construction of Phase 1 of a 3 Phase development...View the site start
- 1 Nov 2022Notice filed · phase 2 · construction of Phase 2 of a 3 Phase development that includes the construction of 28...View the site start
- 15 Nov 2022Notice filed · phase 3 · Construction of Phase 3 of a 3 Phase development that includes the construction of a two...View the site start
- Partial completion certificate recordedRecorded in Sep 2022 · 31 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Nov 2022 · 28 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Nov 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.