Planning record · Co. Kildare

Eadestown GAA, Eadestown, Naas, Co. Kildare

Granted on appeal 2 Dec 2024 (Granted 3 May 2024 by the council)

We no longer update this application, so we can't email you about it. Get new planning applications in Naas by email

Key facts

  • Planning application 231027 at Eadestown GAA, Eadestown, Naas, Co. Kildare: ~6 homes.
  • The applicant is Eadestown GAA. The agent is Pds & Associates.
  • It was received by Kildare County Council on 12 Dec 2023.
  • Status: Granted on appeal 2 Dec 2024 (Granted 3 May 2024 by the council).
  • Work was due to start on 5 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Kildare County Council planning register, as last seen on 5 Oct 2026. Open the council's file

More planning applications in Naas · Planning applications in Co. Kildare

Council register

The council's register shows: Granted on 3 May 2024.

Application details as we last saw them in the national register on 5 Oct 2026.

What and where

~6 homes

change of use from an adjacent agricultural field to a natural grass playing pitch with internal access from existing car park area, additional cark parking spaces, 6 no. 18m high lighting units, a temporary construction access, ball stop netting, pitch fencing, perimeter walking track, a ball wall and scoreboard. Planning permission is also sought to upgrade the existing lighting system on the existing natural grass pitch, to include 6 no. 18m high lighting units and all associated site works

Location
Naas, Co. Kildare Map
Planning reference
231027
Applicant
Eadestown GAA
Agent
Pds & Associates
Architect
Patrick Byrne

Numbers and dates

Homes
~6estimated from the application
Project type
Planning record
Received
12 Dec 2023
Council decision
3 May 2024
Appeal lodged
30 May 2024
Granted on appeal
2 Dec 2024
Site start notified
5 Aug 2025

Timeline

  1. Application received
  2. Granted by the council
  3. Appeal lodged
  4. Appeal decidedGrant permission with revised conditions
  5. Site start notified

Outlook

What happens next

Work was due to start on 5 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Kildare County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 5 Aug 2025Notice filed · The change of use from an adjacent agricultural field to a natural grass playing pitch...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Naas

Get alerts for NaasFree. We email you when new applications appear.

Free email alerts

Get new Naas projects by email

New applications, decisions and site starts in Naas, Co. Kildare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options