Large residential · Co. Limerick

Newtown, Castletroy, Co. Limerick.

Granted 10 Dec 2019 (final grant issued 28 May 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Castletroy by email

Key facts

  • Planning application 19547 at Newtown, Castletroy, Co. Limerick.: 70 homes.
  • It was received by Limerick City and County Council on 6 Jun 2019.
  • Status: Granted 10 Dec 2019 (final grant issued 28 May 2020).

Source: the Limerick City and County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Castletroy · Planning applications in Co. Limerick

Council register

The council's register shows: Granted on 10 Dec 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

70 homes

a residential development comprising 70 no. residential units, (16 no. semi-detached houses, 6 no. terrace houses, 4 no. duplex units, 1 no. 4 storey apartment block over basement), 2 storey Creche and community playing pitch, accessed via the Castletroy College road and all ancillary site development works

Description as published by the council. Its text starts part-way through a sentence.

Location
Castletroy, Co. Limerick Map
Planning reference
19547

Numbers and dates

Homes
70
Floor area
10,886 m²
Estimated construction value
€16m to €30mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
6 Jun 2019
Decision to grant
10 Dec 2019
Final grant
28 May 2020
Site start notified
26 May 2022

Timeline

  1. Application received
  2. Decision to grant
  3. Appeal lodged
  4. Appeal decidedAppeal withdrawn S.140(1)(a)
  5. Final grant issued
  6. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Crèche or childcare facilityNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Limerick City and County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 26 May 2022Notice filed · phase 1 · Construction of 27 Housing Units (No. 32-38, 41-46 and 49-62 inclusive) at Newtown...View the site start
  2. 27 Aug 2022Notice filed · phase 2 · Construction of a apartment block of 31 units at Newtown Meadows, Castletroy, Co. LimerickView the site start
  3. 1 Nov 2022Notice filed · phase 3 · Construction of a 3 storey residential building containing 4 No. Duplex Units at Newtown...View the site start
  4. 5 Sep 2023Notice filed · phase 4 · Construction of a new bike and bin store No. 1 to serve residential units located on the...View the site start
  5. 9 Nov 2023Notice filed · phase 5 · Construction of a new bike and bin store No. 2 to serve residential units located on the...View the site start
  6. Completion certificate recordedRecorded in May 2022 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
  7. Completion certificate recordedRecorded in May 2022 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
  8. Completion certificate recordedRecorded in May 2022 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Castletroy

Get alerts for CastletroyFree. We email you when new applications appear.

Free email alerts

Get new Castletroy projects by email

New applications, decisions and site starts in Castletroy, Co. Limerick. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options