Infrastructure, Annacotty Weir, on the River Mulkear, Townlands of Garraunykee...
I. The full removal (34m) of the Annacotty Weir and fish passage from the eastern riverbank up to the adjacent mill race and sluice gate at the western riverbank and making good the face of retained structural elements. II. The reprofiling and restoration of approximately 50m of the river channel to reinstate natural stream...
The record describes what is sought. Nothing is permitted until the authority decision.
Package signals below are limited to wording in the public application record.
No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.
What the public record evidences
Infrastructure
The public application record identifies infrastructure in the submitted planning scope.
Roads and site-development scope
The public application description explicitly references roads and site-development scope.
Only source-supported scope signals are shown; generic trade padding is omitted.
Named source parties
- Promoter
- Inland Fisheries Ireland
- Planning agent
- Luke Grainger
- Agent address
- O'Connor Sutton Cronin 9 Prussia Street Dublin 7 D07KT57
Application text
I. The full removal (34m) of the Annacotty Weir and fish passage from the eastern riverbank up to the adjacent mill race and sluice gate at the western riverbank and making good the face of retained structural elements. II. The reprofiling and restoration of approximately 50m of the river channel to reinstate natural stream conditions and enable fish migration. This includes placement of boulders, and graded rock to replicate healthy, stable, and natural channel conditions. III. Temporary site access for construction stage is proposed from the Woodstown Road via the existing gateway adjacent to the junction with Mountshannon Road and existing pathway. Creation of a temporary access ramp from the eastern riverbank and temporary stone causeway (with pipes for river flow) on the downstream side of the weir to allow construction vehicle access to the weir from the eastern riverbank; the stone causeway and ramp will be removed as removal of the weir structure progresses. The removal of individual trees to enable construction activities. The creation of temporary construction lay down areas/site compounds on lands approximately 50m to the east of the existing weir. IV. Reinstatement of the disturbed lands following weir removal including landscaping consisting of seeding and planting with appropriate native vegetation, removal of temporary construction facilities, and riverbank restoration works. V. All associated and ancillary site development works. VI. The planning application, including the Natura Impact Statement
Application to site progress
-
Applied 15 Jul 2026 2660806
-
Decision Decision not recorded yet
-
Appeal No appeal possible yet The application has not been decided.
-
Commenced No commencement indexed A scheme cannot start before it is permitted.
-
Completed Completion not recorded Smaller works often do not require a completion certificate.
Source, scope and limits
Application description and scale 2660806
I. The full removal (34m) of the Annacotty Weir and fish passage from the eastern riverbank up to the adjacent mill race and sluice gate at the western riverbank and making good the face of retained structural elements. II. The reprofiling and restoration of approximately 50m of the river channel to reinstate natural stream conditions and enable fish migration. This includes placement of boulders, and graded rock to replicate healthy, stable, and natural channel conditions. III. Temporary site access for construction stage is proposed from the Woodstown Road via the existing gateway adjacent to the junction with Mountshannon Road and existing pathway. Creation of a temporary access ramp from the eastern riverbank and temporary stone causeway (with pipes for river flow) on the downstream side of the weir to allow construction vehicle access to the weir from the eastern riverbank; the stone causeway and ramp will be removed as removal of the weir structure progresses. The removal of individual trees to enable construction activities. The creation of temporary construction lay down areas/site compounds on lands approximately 50m to the east of the existing weir. IV. Reinstatement of the disturbed lands following weir removal including landscaping consisting of seeding and planting with appropriate native vegetation, removal of temporary construction facilities, and riverbank restoration works. V. All associated and ancillary site development works. VI. The planning application, including the Natura Impact Statement
Open official record