Energy · Co. Limerick

Ballygoghlan, Glin, Co. Limerick

Decision due 19 Nov 2026

Get updates on this application

We'll email you when the council decides, if the decision is appealed, and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660943 at Ballygoghlan, Glin, Co. Limerick: Renewable energy development as defined by The European Union.
  • The applicant is Circal Bann Solar Ltd. The agent is Francesca Rowson.
  • It was received by Limerick City and County Council on 14 Aug 2026.
  • Status: Decision due 19 Nov 2026.
  • The council's decision is due on 19 Nov 2026. Building work can only follow a grant of permission.

Source: the Limerick City and County Council planning register, checked 18 Nov 2026. Open the council's file

More planning applications in Glin · Planning applications in Co. Limerick

What and where

Renewable energy development as defined by The European Union

a renewable energy development as defined by The European Union (Planning and Development) (Renewable Energy) Regulations 2025. The Proposed Development, subject of this application, will consist of: The development and operation of a solar photovoltaic (PV) farm with a total area of 245.33 ha, 70.01 ha of which lies within Co. Limerick. The application seeks a 10-year permission with an operational lifetime of 40 years and comprises the following – i. Construction and operation of up to 219,706.1 m² of solar PV arrays on ground-mounted metal frames, with a maximum overall height of up to 2.79 metres. ii. Internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor / transformer skid units. iii. Up to 8 no. electrical inverter / transformer skid units. iv. Construction and operational access to the site by 3 no. site entrances using existing field access points. v. 2 no. temporary construction compounds and ancillary facilities for the duration of the construction phase of the project. vi. Customer substation compound consisting of a single storey substation customer building with welfare facilities (217 m²), all associated electrical plant and apparatus, underground cabling, lighting columns, parking, storage, fencing, wastewater holding tank and rainwater harvesting tank. vii. 33kV collector cable network, joint bays and associated works. viii. Internal access tracks, site landscaping and drainage works, security fencing, CCTV and all associated ancillary site development works. ix. The decommissioning and reinstatement of the solar farm at the end of its operational life. The elements of the Proposed Project located in Co. Limerick, as described above in i – ix, are the subject of this planning application. The remaining elements, including the construction of up to 541,306.68 m² of solar PV arrays on ground-mounted metal frames, with a maximum overall height of up to 2.79 metres, internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor / transformer skid units, up to 19 no. electrical / inverter transformer skid units, construction and operational access to the site by 6 no. site entrances, using 4 no. existing field access points and 2 no. new access points, 3 no. temporary construction compounds and ancillary facilities for the duration of the construction phase of the project, 33kV collector cable network, joint bays and associated works, internal access tracks, site landscaping and drainage works, security fencing, CCTV, all associated ancillary site development works, and decommissioning and reinstatement, are located in the townlands of Kilmurrily, Tarmonhill, Bauragoogeen, Leitrim East, Tarmon East, Shanaway East and Shanaway West, Co. Kerry. This is within the jurisdiction of Kerry County Council, and will be the subject of a separate, concurrent planning application to that Planning Authority. This application is accompanied by a Natura Impact Statement (NIS)

Description as published by the council. Its text starts part-way through a sentence.

Location
Glin, Co. Limerick Map
Planning reference
2660943
Application type
Permission

Numbers and dates

Project type
Energy
Received
14 Aug 2026
Decision due
19 Nov 2026

Outlook

What happens next

The council's decision is due on 19 Nov 2026. Building work can only follow a grant of permission.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660943 on eplanning.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

The August application concerns the Limerick portion of a cross-county solar project. The Kerry works and future 110 kV/grid infrastructure have separate consenting scopes. Arrays, land area and electrical equipment are not building floor area or homes.

3 official documents inspected · Checked 2026-09-07 · Official file index

Limerick scope is 70.01 hectares; total project area differs across official sources

New solar application; whole-project land area differs between the official register and cover · New solar application; no permission or additional residential supply established

What the evidence says
The 14 August cover describes a 243.33 hectare solar project, with 70.01 hectares in Limerick. This application proposes up to 219,706.1 m² of PV arrays and eight inverter/transformer skids in Limerick. The separate Kerry application scope includes up to 541,306.68 m² of arrays and nineteen skids. The key plan draws the two planning boundaries separately.

Why it may matter — interpretation
Solar and civil teams should keep county packages and shared connections distinct when assessing quantities and consenting dependencies.

What is not established
The official register describes 245.33 hectares, while the submitted cover states 243.33 hectares. This 2 hectare discrepancy is unresolved; neither total is selected as agreed. A planning decision, concurrent Kerry outcome, installed capacity and commencement are not established.

Inspect the evidence

Application cover letter and cross-county scope · p.1
Limerick 70.01 ha; whole project 243.33 ha; arrays 219706.1 m² and 8 skids · Issued 2026-08-14 · Cover dated and received 14 August; identifies earlier incomplete 25/60970 · Checked 2026-09-07

Limerick 70.01 ha; whole project 243.33 ha; arrays 219706.1 m² and 8 skids

Application cover letter and cross-county scope · p.2
Separate Kerry scope:541306.68 m² arrays and 19 skids · Issued 2026-08-14 · Cover dated and received 14 August; identifies earlier incomplete 25/60970 · Checked 2026-09-07

Separate Kerry scope:541306.68 m² arrays and 19 skids

Site layout key plan · p.1
250407-04 P01: separate Limerick and Kerry application boundaries · Issued 2026-08-11 · 250407-04 revisionP01, 11 August; county boundaries distinguished · Checked 2026-09-07

250407-04 P01: separate Limerick and Kerry application boundaries

Customer compound is included; 110 kV export infrastructure is reserved for a later application

Current customer/collector scope separated from future grid-consent scope

What the evidence says
The current Limerick proposal includes a 217 m² customer-substation building, welfare facilities and a 33 kV collector network. The cover separately reserves the 110 kV compound, control building, transformer, cabling and future grid connection for another planning application, although the submitted Natura assessment considers that wider infrastructure.

Why it may matter — interpretation
Electrical and civil teams need to identify which compound and cable packages fall within this application before assuming an authorised export connection.

What is not established
Future 110 kV application, grid approval, export capacity and final electrical equipment are not established.

Inspect the evidence

Application cover letter and cross-county scope · p.1
Customer building 217 m² and 33 kV collector network · Issued 2026-08-14 · Cover dated and received 14 August; identifies earlier incomplete 25/60970 · Checked 2026-09-07

Customer building 217 m² and 33 kV collector network

Application cover letter and cross-county scope · p.2
Separate future 110 kV substation and grid application · Issued 2026-08-14 · Cover dated and received 14 August; identifies earlier incomplete 25/60970 · Checked 2026-09-07

Separate future 110 kV substation and grid application

Inverter/transformer enclosure is an illustration subject to manufacturer selection

August planning drawing; illustrative equipment

What the evidence says
The P01 enclosure drawing shows an indicative 6.058 m by 2.438 m plan and 2.896 m height. Its note expressly leaves exact size and appearance to manufacturer selection. These are planning-envelope dimensions rather than confirmed equipment ratings or a purchased package.

Why it may matter — interpretation
Electrical and logistics suppliers need final manufacturer data, maintenance clearances and delivery requirements before fixing foundations or transport plans.

What is not established
Selected manufacturer, electrical rating, heat/noise performance, foundation design and procurement are not established.

Inspect the evidence

Planning drawing pack, part 3 of 3 · p.5
250407-06 P01:6058 x 2438 x 2896 mm; illustration only, manufacturer selection · Issued August 2026 (month only) · PDF p 5 250407-06 P01 10 August; p 6 250407-07 P01 11 August; p 7 250407-08 P01 10 August; p 10 250407-11 10 August, revision not stated; received 14 August · Checked 2026-09-07

250407-06 P01:6058 x 2438 x 2896 mm; illustration only, manufacturer selection

Typical access tracks and fencing leave site-specific construction details open

August typical planning details, not completed works

What the evidence says
The track section shows a minimum 4 m width with crushed stone, geogrid and a permeable separation layer; fill depth is to vary with site conditions. The stock-fence detail includes a 200 mm mammal gap and says exact size and appearance depend on manufacturer selection. Entrance gates are shown opening into the property.

Why it may matter — interpretation
Civil, fencing and ecology teams should coordinate access loadings, ground conditions and wildlife passage before finalising construction details.

What is not established
Ground-investigation design, final track build-up, accepted ecological details and installed fencing are not established.

Inspect the evidence

Planning drawing pack, part 3 of 3 · p.7
250407-08 P01: minimum 4000 mm track; fill depth depends on site · Issued August 2026 (month only) · PDF p 5 250407-06 P01 10 August; p 6 250407-07 P01 11 August; p 7 250407-08 P01 10 August; p 10 250407-11 10 August, revision not stated; received 14 August · Checked 2026-09-07

250407-08 P01: minimum 4000 mm track; fill depth depends on site

Planning drawing pack, part 3 of 3 · p.10
250407-11: stock fence with 200 mm mammal gap · Issued August 2026 (month only) · PDF p 5 250407-06 P01 10 August; p 6 250407-07 P01 11 August; p 7 250407-08 P01 10 August; p 10 250407-11 10 August, revision not stated; received 14 August · Checked 2026-09-07

250407-11: stock fence with 200 mm mammal gap

Planning drawing pack, part 3 of 3 · p.6
250407-07 P01: entrance gates open inward · Issued August 2026 (month only) · PDF p 5 250407-06 P01 10 August; p 6 250407-07 P01 11 August; p 7 250407-08 P01 10 August; p 10 250407-11 10 August, revision not stated; received 14 August · Checked 2026-09-07

250407-07 P01: entrance gates open inward
Remaining document questions
  • Which whole-project land area is correct: the cover’s 243.33 hectares or the official register’s 245.33 hectares?
  • Have the county applications, separate 110 kV grid consent and equipment/ground-design details progressed?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

How we know this

From the Limerick City and County Council planning register, checked 18 Nov 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Glin

Get alerts for GlinFree. We email you when new applications appear.

Free email alerts

Get new Glin projects by email

New applications, decisions and site starts in Glin, Co. Limerick. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options