Large residential · Co. Mayo
Bohernasup, Ballina, Co Mayo
Under appeal since 10 Jul 2025 (Decision to grant 19 Jun 2025 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Ballina by email
Key facts
- Planning application 2560008 at Bohernasup, Ballina, Co Mayo: ~52 homes.
- The applicant is Knocknalyre Limited.
- It was received by Mayo County Council on 20 Dec 2024.
- Status: Under appeal since 10 Jul 2025 (Decision to grant 19 Jun 2025 by the council).
- Work was due to start on 30 Jun 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Mayo County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Ballina · Planning applications in Co. Mayo
Council register
The council's register shows: Decision to grant on 19 Jun 2025.
Appealed to An Coimisiún Pleanála on 10 Jul 2025.
Search the Mayo planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
~52 homes
The development will consist of: (1) Demolition of existing unfinished terrace block structures on site. (2) Construction of a housing development with a total of 52 no. dwellings in detached, semi-detached and terrace configurations, consisting of 20 no. 5-bed detached houses, 6 no. 4-bed semi-detached houses, 4 no. 3-bed semi-detached houses, 10 no. 3-bed terrace houses, 11 no. 2-bed terrace houses and 1 no. 2 bed detached single storey house. (3) Associated development and works including the extension of existing pedestrian and vehicular access to Lansyn Bohernasup, all hard and soft landscaping, internal roads and footpaths, cycle and car parking, public and private amenities and open spaces, boundary treatments, public lighting, and all other ancillary works above and below ground including connections to water supply, surface water infrastructure, wastewater infrastructure and utilities.
- Location
- Ballina, Co. Mayo Map
- Council
- Mayo County Council
- Planning reference
- 2560008
- Applicant
- Knocknalyre Limited
Numbers and dates
- Homes
- ~52estimated from the application
- Floor area
- 6,611 m²per planning documents
- Estimated construction value
- €7.6m to €12mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 20 Dec 2024
- Council decision
- 19 Jun 2025
- Appeal lodged
- 10 Jul 2025
- Site start notified
- 30 Jun 2026
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2560008 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealUnder appeal · 322994 / 10 Jul 2025View the appeal record
- From the planning documentsRead from Application Form - Part A in the council's file.
- Unit mix
- 20 5-bed detached, 6 4-bed semi-detached, 4 3-bed semi-detached, 10 3-bed terrace, 11 2-bed terrace, 1 2-bed detached single storey
- Floor area
- 6,611 m² (per planning documents)
- Site area
- 2.79 ha
- Applicant in the planning documents
- Knocknalyre Limited
- Scope
- Demolition of existing unfinished terrace blocks and construction of 52 dwellings with associated infrastructure, landscaping, and access works.
- Groundworks
- “internal roads and footpaths”
- Rainwater
- “surface water infrastructure”
- Wastewater
- “wastewater infrastructure”
How we know this
From the Mayo County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record. Facts from the planning documents were read from the documents in that file.
Site starts
Commencement notices for this permission
- 30 Jun 2026Notice filed · Construction of a housing development with a total of 50 no. dwellings in detached...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.