Large residential · Co. Offaly

Site west of Father Paul Murphy Street, Edenderry, Co. Offaly

Granted 16 Mar 2026 (final grant issued 20 Apr 2026)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560550 at Site West of Father Paul Murphy Street, Edenderry, Co. Offaly: 92 homes.
  • The applicant is Newlyn Homes Ltd. The agent is Mark Mullally.
  • It was received by Offaly County Council on 12 Nov 2025.
  • Status: Granted 16 Mar 2026 (final grant issued 20 Apr 2026).
  • Work started on site on 17 Jun 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Offaly County Council planning register, checked 2 Jun 2026. Open the council's file

More planning applications in Edenderry · Planning applications in Co. Offaly

What and where

92 homes

92no. Dwellings consisting of: • 19no. Type A Semi Detached 2 Storey 4 Bed Dwelling • 1no. Type A1 Semi Detached 2 Storey 4 Bed Dwelling • 10no. Type B Semi Detached 2 Storey 3 Bed Dwelling • 9no. Type C Ground Floor 1 Bed Maisonette • 1no. Type C2 Ground Floor 1 Bed Maisonette • 9no. Type C1 2 Storey 2 Bed Duplex Maisonette • 1no. Type C3 2 Storey 2 Bed Duplex Maisonette • 20no. Type D Mid Terrace 2 Storey 2 Bed Dwelling • 12no. Type E End Terrace 2 Storey 3 Bed Dwelling • 10no. Type E1 Mid Terrace 2 Storey 3 Bed Dwelling • 2 Storey Creche c.238sq/m • access from Father Paul Murphy Street • internal access roads and footpaths • foul sewers to connect to existing public sewers via on-site temporary treatment system • surface water sewers to connect to existing public sewers • boundary treatments, landscaping and all ancillary site services

Location
Edenderry, Co. Offaly Map
Planning reference
2560550
Applicant
Newlyn Homes Ltd

Numbers and dates

Homes
92
Floor area
7,939 m²
Project type
Large residential
Received
12 Nov 2025
Decision to grant
16 Mar 2026
Final grant
20 Apr 2026
Site start
17 Jun 2026

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start

Outlook

What happens next

Work started on site on 17 Jun 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description
  • Crèche or childcare facilityNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560550 on eplanning.ie: drawings, reports and the decision.Open the council's file
  • From the planning documentsRead from Newlyn Homes Design Statement in the council's file.
    Unit mix
    19 Type A Semi Detached 2 Storey 4 Bed Dwelling, 1 Type A1 Semi Detached 2 Storey 4 Bed Dwelling, 10 Type B Semi Detached 2 Storey 3 Bed Dwelling, 9 Type C Ground Floor 1 Bed Maisonette, 1 Type C2 Ground Floor 1 Bed Maisonette, 9 Type C1 2 Storey 2 Bed Duplex Maisonette, 1 Type C3 2 Storey 2 Bed Duplex Maisonette, 20 Type D Mid Terrace 2 Storey 2 Bed Dwelling, 12 Type E End Terrace 2 Storey 3 Bed Dwelling, 10 Type E1 Mid Terrace 2 Storey 3 Bed Dwelling
    Site area
    4.4 ha
    Applicant
    Newlyn Homes
    Phasing
    Phase 1 – Creche, Units 1-66; Phase 2 – Units 67-92
    Scope
    Residential development of 92 dwellings, a creche, access roads, foul and surface water sewers, boundary treatments, and landscaping on a 4.4-hectare site.

How we know this

From the Offaly County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Site starts

Commencement notices for this permission

  1. 17 Jun 2026Work started · phase 1 · Site Enabling works, to facilitate development of 92 Dwellings, comprising of site...View the site start
  2. 2 Nov 2026Planned start · phase 2 · Construction of 24no units (of 92no) forming phase 1 of 4...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Edenderry

Get alerts for EdenderryFree. We email you when new applications appear.

Free email alerts

Get new Edenderry projects by email

New applications, decisions and site starts in Edenderry, Co. Offaly. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options