Energy · Co. Offaly

Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore, County, Offaly

Decision to grant 20 May 2026

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660071 at Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore, County, Offaly: Amendment to a previously consented development.
  • The applicant is Ballyteige Solar Ltd. The agent is Colleen Patterson.
  • It was received by Offaly County Council on 11 Feb 2026.
  • Status: Decision to grant 20 May 2026.
  • The council decided on 20 May 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

Source: the Offaly County Council planning register, checked 2 Jun 2026. Open the council's file

Planning applications in Co. Offaly

What and where

Amendment to a previously consented development

an amendment to a previously consented development (RED III) (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km, relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares and comprises of a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III). This planning application is accompanied by a Natura Impact Statement (NIS). This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Description as published by the council. Its text starts part-way through a sentence.

Location
County, Co. Offaly Map
Planning reference
2660071

Numbers and dates

Project type
Energy
Received
11 Feb 2026
Decision to grant
20 May 2026Final grant not yet recorded

Timeline

  1. Application received
  2. Decision to grant

Outlook

What happens next

The council decided on 20 May 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660071 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Offaly County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near County

Get alerts for Co. OffalyFree. We email you when new applications appear.

Free email alerts

Get new Offaly projects by email

New applications, decisions and site starts in Co. Offaly. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options