Public / civic · Co. Tipperary
Ballina Primary School, Ballina, Co. Tipperary
Granted 6 Aug 2019 (final grant issued 10 Sep 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Ballina by email
Key facts
- Planning application 19600660 at Ballina Primary School, Ballina, Co. Tipperary: Single storey split level extension to rear of existing school.
- It was received by Tipperary County Council on 14 Jun 2019.
- Status: Granted 6 Aug 2019 (final grant issued 10 Sep 2019).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Ballina · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 6 Aug 2019.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Single storey split level extension to rear of existing school
a single storey split level extension to rear of existing school including alterations and all associated site works.
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Ballina, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 19600660
Numbers and dates
- Project type
- Public / civic
- Received
- 14 Jun 2019
- Decision to grant
- 6 Aug 2019
- Final grant
- 10 Sep 2019
- Site start notified
- 14 Mar 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 19600660 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 14 Mar 2022Notice filed · Single storey extension to rear of existing school, including all associated site worksView the site start
- Completion certificate recordedRecorded in Mar 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.