Commercial new build · Co. Tipperary
Gortlandroe Business Park, Gortlandroe Road, Gortlandroe Nenagh, Co. Tipperary
Granted 30 Sep 2019 (final grant issued 4 Nov 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Tipperary by email
Key facts
- Planning application 19600902 at Gortlandroe Business Park, Gortlandroe Road, Gortlandroe Nenagh, Co. Tipperary: Modification to previously granted permission Ref No 18600660…
- It was received by Tipperary County Council on 16 Aug 2019.
- Status: Granted 30 Sep 2019 (final grant issued 4 Nov 2019).
- Work was due to start on 22 Aug 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 30 Sep 2019.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Modification to previously granted permission Ref No 18600660…
modification to previously granted permission Ref No 18600660 for construction of a new warehouse building and all ancillary site works, the modification consists of raised ridge and roof heights
- Location
- Gortlandroe Nenagh, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 19600902
Numbers and dates
- Project type
- Commercial new build
- Received
- 16 Aug 2019
- Decision to grant
- 30 Sep 2019
- Final grant
- 4 Nov 2019
- Site start notified
- 22 Aug 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission 18600660 for this site: granted 23 Aug 2018.
construction of a new warehouse building and all ancillary site works Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 19600902 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 22 Aug 2024Notice filed · Erection of new warehouse building at Gortlandroe Business Park, NenaghView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.