Public / civic · Co. Tipperary
Burncourt National School, Burncourt, Cahir, Co. Tipperary
Granted 31 Jul 2020 (final grant issued 3 Sep 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Cahir by email
Key facts
- Planning application 20599 at Burncourt National School, Burncourt, Cahir, Co. Tipperary: New single storey extension to the north-east elevation…
- It was received by Tipperary County Council on 16 Jun 2020.
- Status: Granted 31 Jul 2020 (final grant issued 3 Sep 2020).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Cahir · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 31 Jul 2020.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New single storey extension to the north-east elevation…
construction of new single storey extension to the north-east elevation and to the rear of existing primary school building, to accommodate 3 no. mainstream classrooms with ancillary accommodation including w.c.s and new boiler house. Ancillary works to include: minor elevational alterations to existing school building; removal from site of existing boiler house; removal of 1 no. existing temporary prefabricated unit; removal of 1 no. existing covered shelter and removal of existing oil tank and installation of new enclosed (1.8m high fencing) oil tank and all associated site works
- Location
- Cahir, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 20599
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- Public / civic
- Received
- 16 Jun 2020
- Decision to grant
- 31 Jul 2020
- Final grant
- 3 Sep 2020
- Site start notified
- 14 Apr 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 20599 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 14 Apr 2021Notice filed · Construction of new single storey extension to the existing primary school building and...View the site start
- Completion certificate recordedRecorded in Apr 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.