Small residential · Co. Tipperary
Ballyknock, Cashel, Co. Tipperary
Granted 29 Apr 2022 (final grant issued 2 Jun 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Cashel by email
Key facts
- Planning application 211383 at Ballyknock, Cashel, Co. Tipperary: 2 homes.
- It was received by Tipperary County Council on 17 Sep 2021.
- Status: Granted 29 Apr 2022 (final grant issued 2 Jun 2022).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Cashel · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 29 Apr 2022.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
2 homes
new two storey dwelling, domestic garage, alterations to existing site entrance, new septic tank and percolation area and all associated site works
- Location
- Cashel, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 211383
Numbers and dates
- Homes
- 2
- Floor area
- 305 m²
- Estimated construction value
- €460k to €590kOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Small residential
- Received
- 17 Sep 2021
- Decision to grant
- 29 Apr 2022
- Final grant
- 2 Jun 2022
- Site start notified
- 19 Jun 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 211383 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 19 Jun 2023Notice filed · New two storey dwelling, domestic garage, alterations to existing site entrance, new...View the site start
- Completion certificate recordedRecorded in Jun 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.