  • Planning application 2260226 at Lisnareelin, Killea, Templemore, Co. Tipperary: New detached single storey dwelling.
  • It was received by Tipperary County Council on 16 May 2022.
  • Status: Granted 29 Jun 2022 (final grant issued 2 Aug 2022).
  • Work was due to start on 13 Mar 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Templemore · Planning applications in Co. Tipperary

Council register

The council's register shows: Granted on 29 Jun 2022.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New detached single storey dwelling

a) construction of a new detached single storey dwelling; b) new detached garage; c) new site entrance; d) new connections to existing utilities; e) new waste-water treatment system & percolation area; f) all associated site works

Description as published by the council. Its text starts part-way through a sentence.

Location
Templemore, Co. Tipperary Map
Planning reference
2260226

Numbers and dates

Homes
1
Floor area
240 m²
Project type
One-off house
Received
16 May 2022
Decision to grant
29 Jun 2022
Final grant
2 Aug 2022
Site start notified
13 Mar 2023

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 13 Mar 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2260226 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 13 Mar 2023Notice filed · phase 1 · Construction of a new detached single storey dwelling; new site entrance; new...View the site start
  2. 14 Mar 2023Notice filed · phase 2 · Construction of domestic GarageView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Templemore

Get alerts for TemplemoreFree. We email you when new applications appear.

Free email alerts

Get new Templemore projects by email

New applications, decisions and site starts in Templemore, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options