Site start · Co. Tipperary
Nenagh, Tipperary
Granted 27 Jun 2023 (final grant issued 31 Jul 2023)
Key facts
- Site start record 2260527 at Nenagh, Co. Tipperary: 91 homes.
- The planning authority is Tipperary County Council.
- Status: Granted 27 Jun 2023 (final grant issued 31 Jul 2023).
Source: the Tipperary County Council planning register, as last seen on 12 Jul 2026. Open the council's file
More planning applications in Nenagh · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 27 Jun 2023.
Search the Tipperary planning register
Application details as we last saw them in the national register on 12 Jul 2026.
What and where
91 homes
91 no. residential units that will comprise the following: a) 10 no. 4 bed 2-storey detached houses (Type A), b) 1 no. 4 bed 2-storey detached house (Type B), c) 32 no. 4 bed 2-storey semi-detached houses (Type C & Ch’), d) 9 no. 4 bed 2-storey semi-detached houses (Type D & Dh’), e) 5 no. 4 bed 2-storey semi-detached houses (Type E & Eh’), f) 32 no. 3 bed 2-storey semi-detached houses (Type F & Fh’), g) 1 no. 3 bed 2-storey semi-detached house (Type G), h) 1 no. 3 bed 2-storey semi-detached house (Type H). Planning permission is also sought for the construction of a new single storey Crèche consisting of the following at ground floor level; 4 no. class rooms, sleep room, kitchens, toilets, stores, staff room, office, reception and associated ancillary areas, together with new vehicular and pedestrian entrance, boundary treatments, new car parking and set down area, bin store, external play area and signage. Planning permission is also sought for the demolition of 1 number unfinished 2 storey dwelling. Planning permission is also sought for all associated site works to include the following: New vehicular road and pedestrian access from the existing access on Dromin Road, new vehicular roads and pedestrian accesses from the extended access road, new boundary treatments, landscaping, public lighting, car parking, signage, ESB sub-station and switch room, together with all associated drainage connection works to include proposed surface water drainage to existing watercourse on Western boundary, proposed connection to existing foul sewer within site, water supply connection from existing water supply within site. A Natura Impact Statement is with this application
- Location
- Nenagh, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2260527
- Application type
- Commencement Notice
- Owner named on the notice
- Dromin Nenagh Property Development LTD
- Agent named on the notice
- Quantum Homes Ltd
Numbers and dates
- Homes
- 91
- Floor area
- 11,137 m²
- Estimated construction value
- €16m to €22mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Mixed use
- Received
- 30 Sep 2022
- Decision to grant
- 27 Jun 2023
- Final grant
- 31 Jul 2023
- Site start notified
- 6 Feb 2026
Documents and evidence
Check the record
- Council planning fileThe application file 2260527 on eplanning.ie: drawings, reports and the decision.Open the council's file
- From the planning documentsRead from design statement phase 1 in the council's file.
- Unit mix
- 10 Type A - 4/5 bedroom two storey detached houses, 1 Type B - 4 bedroom two storey detached house, 32 Type C - 4 bedroom two storey semi-detached houses, 9 Type D - 4/5 bedroom two storey semi-detached, 5 Type E - 4 bedroom two storey semi-detached houses, 32 Type F - 3 bedroom two storey semi-detached houses, 1 Type G – 3 bedroom two storey semi-detached house, 1 Type H – 3 bedroom two storey semi-detached house
- Site area
- 3.43 ha
- Applicant in the planning documents
- Dromin Nenagh Property Development LTD
- Phasing
- Phase 1 of a 4-phase masterplan, includes creche, sport pitches, and commercial area.
- Scope
- Phase 1 proposes 91 residential units and a creche for 84 children on 3.43 hectares at Dromin Road, Nenagh.
- Groundworks
- “distributor road connecting to Dromin Rd”
How we know this
From the Tipperary County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record. Facts from the planning documents were read from the documents in that file.
Site starts
Commencement notices for this permission
- 6 Feb 2026Notice filed · Construction of units 1-9 The Grove, 1-6 and 38-41 The Avenue, 1-6 The Green and 1-6 The...View the site start