Planning record · Co. Tipperary
Clonmore, Templemore, Co. Tipperary
Granted 20 Mar 2023 (final grant issued 23 Apr 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Templemore by email
Key facts
- Planning application 2360059 at Clonmore, Templemore, Co. Tipperary: Prefabricated building.
- It was received by Tipperary County Council on 31 Jan 2023.
- Status: Granted 20 Mar 2023 (final grant issued 23 Apr 2023).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Templemore · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 20 Mar 2023.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Prefabricated building
a prefabricated building including all associated site works and RETENTION permission is also sought for an existing storage shed
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Templemore, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2360059
Numbers and dates
- Project type
- Planning record
- Received
- 31 Jan 2023
- Decision to grant
- 20 Mar 2023
- Final grant
- 23 Apr 2023
- Site start notified
- 23 Jun 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 2360059 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 23 Jun 2023Notice filed · Single Storey Temporary accommodation and associated site worksView the site start
- Completion certificate recordedRecorded in Jun 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.