Planning record · Co. Tipperary
Ballylynch, Carrick-on-Suir, Co. tipperary
Granted 2 May 2023 (final grant issued 5 Jun 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Carrick-On-Suir by email
Key facts
- Planning application 2360162 at Ballylynch, Carrick-on-Suir, Co. Tipperary: Two extensions to existing mixed dry recycling building.
- It was received by Tipperary County Council on 9 Mar 2023.
- Status: Granted 2 May 2023 (final grant issued 5 Jun 2023).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Carrick-On-Suir · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 2 May 2023.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Two extensions to existing mixed dry recycling building
two extensions to existing mixed dry recycling building including all associated site development works
- Location
- Carrick-On-Suir, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2360162
Numbers and dates
- Project type
- Planning record
- Received
- 9 Mar 2023
- Decision to grant
- 2 May 2023
- Final grant
- 5 Jun 2023
- Site start notified
- 2 Oct 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2360162 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 2 Oct 2023Notice filed · Structural steel extension to cover part of yard at Quality Recycling Ltd.View the site start
- Completion certificate recordedRecorded in Oct 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.