Commercial new build · Co. Tipperary

MSD Ireland (Ballydine), Ballydine Kilsheelan Clonmel, Co. Tipperary

Granted 18 Jul 2025 (final grant issued 21 Aug 2025)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560487 at MSD Ireland (Ballydine), Ballydine Kilsheelan Clonmel, Co. Tipperary: MV electrical building.
  • The applicant is Msd Ireland (Ballydine. The agent is David Moore.
  • It was received by Tipperary County Council on 29 May 2025.
  • Status: Granted 18 Jul 2025 (final grant issued 21 Aug 2025).
  • Work started on site on 25 Sep 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Tipperary County Council planning register, checked 2 Jun 2026. Open the council's file

Planning applications in Co. Tipperary

What and where

MV electrical building

the construction of an MV electrical building. The development will consist of: i) a new MV electrical building to comprise electrical rooms over an under-croft level to provide a gross floor area of approximately 168.8 square meters and a maximum height of 4.76 metres to include grated steel access platforms; ii) all associated site development and ancillary works including modifications to footpaths, drainage and utility services, and ground works. The proposed development is located on a site that operates under an existing Industrial Emissions (IE) Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act, 2003). The proposed development is on a site which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 applies

Description as published by the council. Its text starts part-way through a sentence.

Location
Ballydine Kilsheelan Clonmel, Co. Tipperary Map
Planning reference
2560487
Applicant
Msd Ireland (Ballydine
Council planning fileGet alerts

Numbers and dates

Floor area
169 m²
Estimated construction value
€170k to €230kOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Commercial new build
Received
29 May 2025
Decision to grant
18 Jul 2025
Final grant
21 Aug 2025
Site start
25 Sep 2025

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start

Outlook

What happens next

Work started on site on 25 Sep 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Work packages named so far

  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560487 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Tipperary County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Site starts

Commencement notices for this permission

  1. 25 Sep 2025Work started · MSD Ballydine Project BACE – Construction of MV Building (SUB09)

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Ballydine Kilsheelan Clonmel

Get alerts for Co. TipperaryFree. We email you when new applications appear.

Free email alerts

Get new Tipperary projects by email

New applications, decisions and site starts in Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options