Large residential · Co. Tipperary

Croan Lower, Coleville Road, Clonmel, Co. Tipperary

Decision due 7 Dec 2026

Get updates on this application

We'll email you when the council decides, if the decision is appealed, and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 26115 at Croan Lower, Coleville Road, Clonmel, Co. Tipperary: ~115 homes.
  • The applicant is Torca Developments Ltd. The agent is McGill Planning Ltd.
  • It was received by Tipperary County Council on 10 Aug 2026.
  • Status: Decision due 7 Dec 2026.
  • The council's decision is due on 7 Dec 2026. Building work can only follow a grant of permission.

Source: the Tipperary County Council planning register, checked 19 Nov 2026. Open the council's file

More planning applications in Clonmel · Planning applications in Co. Tipperary

What and where

~115 homes

development which will consist of 115 no. residential units comprising 5 no. 3 storey blocks with 14 no. 1 bed apartments, 9 no. 2 bed apartments and 24 no. 3 bed duplexes; and 68 no. 2 storey houses (24 no. 2-bed houses, 24 no. 3-bed houses and 20 no. 4 bed houses). A 2-storey creche (c.208 m²), 181 no. car parking spaces, 366 no. cycle parking spaces, open spaces, bin stores and ESB substations. The proposal includes for a new vehicular and pedestrian access and upgrades along the Coleville Road (R680). All associated site development works (including site reprofiling), landscaping, boundary treatments and services connections

Location
Clonmel, Co. Tipperary Map
Planning reference
26115
Application type
Extention of duration
Applicant
Torca Developments Ltd

Numbers and dates

Homes
~115estimated from the application
Estimated construction value
€17m to €32mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
10 Aug 2026
Decision due
7 Dec 2026

Timeline

  1. Application received
  2. Further information requested
  3. Further information received

Outlook

What happens next

The council's decision is due on 7 Dec 2026. Building work can only follow a grant of permission.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description
  • Crèche or childcare facilityNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 26115 on eplanning.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

This is an August 2026 application to extend an existing permission, not a new 115-home scheme. Submitted material describes work already underway and contains differing 115, 122 and 123-unit scopes. The programme is a forecast; neither a granted extension nor current completion is established.

4 official documents inspected · Checked 2026-09-07 · Official file index

Duration request concerns original Board permission ABP-311290-21

Application context; the duration extension is not established as granted · Directional permission context; separate identities and quantities remain unchanged

What the evidence says
The August cover requests an extension of duration of ABP-311290-21 for the existing development. It quotes the original grant of 17 December 2021 and an applicant-calculated expiry of 30 January 2027. The current application seeks completion time; it does not establish a granted extension or fresh 115-home supply.

Why it may matter — interpretation
Planning and construction teams can follow the permission history without treating a time-extension request as additional supply.

What is not established
No granted duration extension, new commencement or merged permission total is established.

Inspect the evidence

Duration-extension cover letter and supporting report · p.1
Extension of duration: ABP-311290-21 · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

Extension of duration: ABP-311290-21

Submitted August report describes advanced early phases and incomplete later work

Applicant-reported progress in the August submission, not a fresh site inspection

What the evidence says
The cover reports phase 1 homes with roofs complete or nearly complete and windows/doors installed or in manufacture; phase 2 A roofs and windows substantially complete; and phase 2 B substructures with deep drainage. It also reports completed electrical ducting, external water connection and surface-water outfall, with further earthworks and substructure across later phases. Submitted photographs show buildings and services under construction.

Why it may matter — interpretation
Finishing, services and external-works suppliers can distinguish reported advanced shells from later structural work while checking present progress.

What is not established
Current site status, independent completion certification, live procurement availability and completed occupation are not established.

Inspect the evidence

Duration-extension cover letter and supporting report · p.4
Reported phased construction and utility progress · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

Reported phased construction and utility progress

Duration-extension cover letter and supporting report · p.5
Submitted photographs of phase 1 structures and site services · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

Submitted photographs of phase 1 structures and site services

Amended permission scope is 122 homes; the later report of 123 remains unexplained

Original permission scope, amended drawing and later reported programme scope remain distinct

What the evidence says
The original layout schedules 115 homes. The amended layout schedules 122 homes, and page 9 of the August cover identifies ABP-320189-24 as the amendment permitting 122 homes (76 houses and 46 apartments), with its life tied to parent ABP-311290-21. Page 4 of the same cover reports delivery of 123 homes. That extra reported home is not explained by the reviewed permission scope and must not be treated as a newly agreed total.

Why it may matter — interpretation
Planning and quantity teams should reconcile the governing amendments before using the estate total for remaining-work or housing-supply calculations.

What is not established
A complete amendment chain reconciling 122 and 123 and an independently verified remaining-home count are not established.

Inspect the evidence

Original and amended site layouts submitted with extension · p.2
PA-100 revA:115 units · Issued Not stated · PDF p 2 project 5387 PA-100 revA, July 2021, 115 units; PDF p 3 project 5602 PL-100 revA, June 2023, 122 units; received 10 August 2026; pack issue date not stated · Checked 2026-09-07

PA-100 revA:115 units

Original and amended site layouts submitted with extension · p.3
PL-100 revA:122 units, 7 additional · Issued Not stated · PDF p 2 project 5387 PA-100 revA, July 2021, 115 units; PDF p 3 project 5602 PL-100 revA, June 2023, 122 units; received 10 August 2026; pack issue date not stated · Checked 2026-09-07

PL-100 revA:122 units, 7 additional

Duration-extension cover letter and supporting report · p.4
Cover describes orderly completion delivering 123 homes · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

Cover describes orderly completion delivering 123 homes

Duration-extension cover letter and supporting report · p.9
Amended permission scope and common duration · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

ABP-320189-24 amended permission: 122 residential units, 76 houses and 46 apartments; life tied to ABP-311290-21

Submitted programme forecasts phased completion through August 2028

Forecast remaining-work programme, subject to the unresolved extension

What the evidence says
The June programme schedules remaining work from September 2026, with phase 1 completion in June 2027 and overall practical completion on 7 August 2028. These are submitted target dates supporting the duration request. The already-reported construction means its September start line is not proof that the whole development first commenced then.

Why it may matter — interpretation
Contractors and suppliers should verify updated sequencing and available packages against actual site progress and the extension outcome.

What is not established
An approved extended period, updated contractor programme and achieved milestone dates are not established.

Inspect the evidence

Submitted construction programme · p.1
Programme 21 June: phase 1 finish 16 June 2027; all-phases practical completion 7 August 2028 · Issued 2026-06-21 · Programme dated 21 June; revised baseline 7 June; received 10 August; forecast remaining works · Checked 2026-09-07

Programme 21 June: phase 1 finish 16 June 2027; all-phases practical completion 7 August 2028

Duration-extension cover letter and supporting report · p.4
Works already underway across phases before the programme start line · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

Works already underway across phases before the programme start line

Board amendment ABP-320189-24 forms part of the permission history

Application context; the duration extension is not established as granted · Directional permission context; separate identities and quantities remain unchanged

What the evidence says
Page 9 of the August submission identifies ABP-320189-24 as amending the scheme to 122 homes and states that condition 2 ties its life to parent ABP-311290-21. This is context for the duration request, with the two Board case files kept separate.

Why it may matter — interpretation
Planning and construction teams can follow the permission history without treating a time-extension request as additional supply.

What is not established
No granted duration extension, new commencement or merged permission total is established.

Inspect the evidence

Duration-extension cover letter and supporting report · p.9
ABP-320189-24; 122 residential units; condition 2 ties life to ABP-311290-21 · Issued 2026-08-07 · Dated 7 August, received 10 August; references ABP-311290-21; work progress is applicant-reported · Checked 2026-09-07

ABP-320189-24; 122 residential units; condition 2 ties life to ABP-311290-21

Council amendment 24/60316 is explicitly referenced in the submitted support

Application context; the duration extension is not established as granted · Directional permission context; separate identities and quantities remain unchanged

What the evidence says
The submitted ecology letter identifies the original Board permission and the council amendment 24/60316. This supports a separate permission-history link; it does not establish an outcome for the 2026 duration request. The letter is printed 4 August 2025 and was received in the current case on 10 August 2026.

Why it may matter — interpretation
Planning and construction teams can follow the permission history without treating a time-extension request as additional supply.

What is not established
No granted duration extension, new commencement or merged permission total is established.

Inspect the evidence

Submitted ecology supporting letter identifying the parent and council amendment · p.1
Amendments approved in 2024; Planning Ref. 24/60316 · Issued 2025-08-04 · Printed 4 August 2025; council received stamp 10 August 2026 · Checked 2026-09-07

Amendments approved in 2024; Planning Ref. 24/60316
Remaining document questions
  • Has the duration request been determined, and why does the August progress narrative report 123 homes against the documented amended permission scope of 122?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

How we know this

From the Tipperary County Council planning register, checked 19 Nov 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Clonmel

Get alerts for ClonmelFree. We email you when new applications appear.

Free email alerts

Get new Clonmel projects by email

New applications, decisions and site starts in Clonmel, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options