  • Planning application 2660621 at Thornhill and Annaholty, Birdhill, Co. Tipperary: RED III development which will consist of planning permission…
  • The applicant is Annaholty Green Energy Ltd. The agent is Anna D'Arcy.
  • It was received by Tipperary County Council on 25 Jun 2026.
  • Status: Further information requested 29 Sep 2026.
  • The council asked for further information on 29 Sep 2026. It decides after the applicant replies.

Source: the Tipperary County Council planning register, checked 11 Nov 2026. Open the council's file

More planning applications in Birdhill · Planning applications in Co. Tipperary

What and where

RED III development which will consist of planning permission…

RED III development which will consist of planning permission for a period of 10 years for the construction and operation of a biogas renewable energy facility comprising of 2 no. primary anaerobic digesters (height c. 18.5m); 1 no. secondary digester/storage tank (dome height c. 16.5m); 1 no. digestate storage tank (dome height c. 16.5m); 2 no. manure reception tanks (dome height c. 12m); 1 no. desulphurisation unit (ground floor area (GFA) c. 13 m², height c. 3.3m), 1 small tank (height c. 3.2m) and 2 larger tanks (height c 9.8m & c 11.8m); 2 no. pasteurization tanks (height c. 5.6m) and 2 no. cooling tanks (height c. 5.6m); 1 no. external Solid Input Device (SID); 1 no. pump room (GFA 300 m², height 3.1m); these components will be located within a containment bund (height c. 1.5m). The proposed development will also consist of: 1 no. feedstock reception hall (GFA 1,800 m², height c.15m) with air filtration unit (stack height c. 20.5m), 1 no. underground mixing tank (diameter c.16m, height c. 4m), 1 no. SID, offices, and workshop; 5 no. silage clamps (GFA 8,640 m², height c. 5m); 1 no. storage shed (GFA 228 m², height c. 5m); 1 no. rainwater harvesting tank (height c. 6m); 1 no. fire water storage tank (height c. 5.5m); 1 no. plant room (GFA c. 90 m², height c. 5.3m); 2 no. CHP units and chillers (GFA 44 m² each, maximum height c. 7.5m to flue); 1 no. bunded biofuel tank (length c. 6.2m, height c. 2.3m); and diesel tank (length c. 4m, height 2.5m); 1 no. dewatering storage building (GFA c. 263 m², height c. 5.5m) with air filtration unit (stack height c. 9.5m); 1 no. ESB substation building (GFA c. 65 m², height c. 3.8m); 1 no. biomethane upgrade unit (GFA c. 235 m², height c. 13.2m); 1 no. carbon dioxide capture unit (GFA c. 885 m², height c. 16.7m); 1 no. two storey admin building containing offices, laboratories, and welfare facilities (GFA 228 m², height c. 8.2m); 1 no LPG compound (GFA 98 m²) with bunded wall (height c. 2.5m) containing 2 no. propane tanks (diameter c. 1.5m, length c. 4.8m); 1 no. emergency flare (height c. 7.7m); 1 no. Gas Networks Ireland (‘GNI’) compound (‘Biomethane Network Entry Facility’) kiosk (GFA c. 24 m², height c. 5.1m (antenna)) with two parking bays; firewater retention pond (c. 1,750m3); infiltration basin (c. 2300m3); underground silage clamp tank, (c. 3,725m3), boundary treatments and ancillary works that will include: tree felling to facilitate construction and operation of the proposed development; new site entrance off the L94451, security gates and fencing; access roads with a passing bay and yards; 1 no. weighbridge; 2 no. wheel washes; bunding; surface water drainage system; foul wastewater holding tank and equipment; vehicular parking with charging (HGV, cars and bicycles); landscaping, planting (c. 3.65ha) of broadleaf woodland, and berms (height c. 1-3m); lighting, a passing bay at the L94451/R445 junction and all ancillary works. Servicing arrangements will include the provision of potable water mains, GNI gas connection via the GNI compound; ESB substation and transformer. An Environmental Impact Assessment Report (‘EIAR’) and Natura Impact Statement (‘NIS’) will be submitted as part of the planning application. An Industrial Emissions Licence (‘IEL’) will be required for the operation of this development under the provisions of the Environmental Protection Agency Act 1992, as amended. An application for this IEL will be made to the EPA post grant of planning. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Location
Birdhill, Co. Tipperary Map
Planning reference
2660621
Application type
Permission
Applicant
Annaholty Green Energy Ltd

Numbers and dates

Received
25 Jun 2026

Timeline

  1. Application received
  2. Further information requested

Outlook

What happens next

The council asked for further information on 29 Sep 2026. It decides after the applicant replies.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660621 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Tipperary County Council planning register, checked 11 Nov 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Birdhill

Get alerts for BirdhillFree. We email you when new applications appear.

Free email alerts

Get new Birdhill projects by email

New applications, decisions and site starts in Birdhill, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options