Infrastructure · Co. Tipperary
ESB Doon 110 kV Substation, Ballyvaughan, Clonmel Co. Tipperary
Granted 6 Oct 2026 (final grant issued 9 Nov 2026)
Key facts
- Planning application 2660648 at ESB Doon 110 kV Substation, Ballyvaughan, Clonmel Co. Tipperary: RED III development which will consist of the provision of new…
- The applicant is Electricity Supply Board.
- It was received by Tipperary County Council on 3 Jul 2026.
- Status: Granted 6 Oct 2026 (final grant issued 9 Nov 2026).
- Permission was granted on 6 Oct 2026 and the final grant issued on 9 Nov 2026. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.
Source: the Tipperary County Council planning register, checked 19 Nov 2026. Open the council's file
More planning applications in Ballyvaughan · Planning applications in Co. Tipperary
What and where
RED III development which will consist of the provision of new…
RED III development which will consist of the provision of new electrical plant and equipment, including; 1 no. existing Arc Suppression Coil to be retired and replace with 1 no. new Arc Suppression Coil, extension to control room building (c. 27 m²), associated and ancillary outdoor electrical equipment and other apparatus, including installation of underground cables; and all other ancillary works. (This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply)
- Location
- Ballyvaughan, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2660648
- Application type
- Permission
- Applicant
- Electricity Supply Board
Numbers and dates
- Floor area
- 27 m²
- Project type
- Infrastructure
- Received
- 3 Jul 2026
- Decision to grant
- 6 Oct 2026
- Final grant
- 9 Nov 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2660648 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, checked 19 Nov 2026. We link to the council's own file so you can check the official record before you act.