~54 dwellings, Lands at Crann Ard and Glencarra Estates, Fethard Road, Clonmel
a development which will consist of the construction of a residential development of 54 no. houses, comprising 7 no. single-storey, 3-bed detached units; 24 no. two-storey, 3-bed semi-detached units; 12 no. two-storey, 3-bed terraced units and 11 no. two-storey, 2-bed terraced units; 119 no. car parking spaces...
The record describes what is sought. Nothing is permitted until the authority decision.
Package signals below are limited to wording in the public application record.
No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.
What the public record evidences
Large residential - 54 dwellings
The public application record identifies 54 dwellings in the submitted planning scope.
Roads and site-development scope
The public application description explicitly references roads and site-development scope.
Services / drainage scope
The public application description explicitly references services / drainage scope.
Only source-supported scope signals are shown; generic trade padding is omitted.
Named source parties
- Promoter
- Bluemont Developments (Clonmel) Ltd
- Planning agent
- Donal Duffy
- Agent address
- DOWNEY 29 Merrion Square Dublin 2 D02RW64
- Builder / developer
- Bluemont Developments (Clonmel) Ltd.
Facts extracted from official planning documents
- Unit mix
- 7 3-bed detached, 24 3-bed semi-detached, 12 3-bed terraced, 11 2-bed terraced
- Floor area (per planning documents)
- 5,402 m²
- Site area
- 2.12 ha
- Applicant / promoter
- Bluemont Developments (Clonmel) Ltd.
- Phasing
- Single phase
- Scope
- Construction of 54 residential units with associated parking, landscaping, and site works including junction upgrade.
Facts only; drawings and document packs are not republished.
Source: Architectural Design Statement, Tipperary County Council planning file
Application text
a development which will consist of the construction of a residential development of 54 no. houses, comprising 7 no. single-storey, 3-bed detached units; 24 no. two-storey, 3-bed semi-detached units; 12 no. two-storey, 3-bed terraced units and 11 no. two-storey, 2-bed terraced units; 119 no. car parking spaces (97 no. in-curtilage spaces and 22 no. shared visitor spaces); bicycle parking; an ESB substation; refuse staging areas; landscaping; boundary treatment; public lighting and all ancillary site development works including removal of any existing foundations and structures, provisions for foul, surface water and potable water services and the upgrading of the R689 and Crann Ard junction to a signalised junction
Application to site progress
-
Applied 21 Jul 2026 2660709
-
Decision Decision not recorded yet
-
Appeal No appeal possible yet The application has not been decided.
-
Commenced No commencement indexed A scheme cannot start before it is permitted.
-
Completed Completion not recorded Smaller works often do not require a completion certificate.
Source, scope and limits
Application description and scale 2660709
a development which will consist of the construction of a residential development of 54 no. houses, comprising 7 no. single-storey, 3-bed detached units; 24 no. two-storey, 3-bed semi-detached units; 12 no. two-storey, 3-bed terraced units and 11 no. two-storey, 2-bed terraced units; 119 no. car parking spaces (97 no. in-curtilage spaces and 22 no. shared visitor spaces); bicycle parking; an ESB substation; refuse staging areas; landscaping; boundary treatment; public lighting and all ancillary site development works including removal of any existing foundations and structures, provisions for foul, surface water and potable water services and the upgrading of the R689 and Crann Ard junction to a signalised junction
Open official record