Temporary/event · Co. Tipperary

~17 homes, Cashel, Co. Tipperary

Decision due 29 Nov 2026

Get updates on this application

We'll email you when the council decides, if the decision is appealed, and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660834 at Cashel, Co. Tipperary: ~17 homes.
  • The applicant is Patricks Rock Solar Ltd. The agent is Niamh McHugh.
  • It was received by Tipperary County Council on 28 Aug 2026.
  • Status: Decision due 29 Nov 2026.
  • The council's decision is due on 29 Nov 2026. Building work can only follow a grant of permission.

Source: the Tipperary County Council planning register, checked 22 Oct 2026. Open the council's file

More planning applications in Cashel · Planning applications in Co. Tipperary

What and where

~17 homes

RED III development - construction of a solar photovoltaic (PV) energy development with a total site area of 151 hectares. The proposed development includes for the erection of solar panels on ground-mounted galvanised steel frames, 17 no. transformer units, a permanent operations compound, inverters, underground cabling and ducting, security fencing, pole mounted closed circuit television (CCTV) cameras, upgrade of 5 no. existing site entrances, construction of 1 no. new site entrance, internal site access tracks, landscaping, 1 no. temporary construction compound, 4 no. satellite compounds, temporary laydown areas and all associated development works. The operational lifespan of the solar PV development will be 40 years. The proposed development will incorporate a grid connection which will be subject to a separate planning application at a later date. The planning application is accompanied by a Natura Impact Statement

Location
Cashel, Co. Tipperary Map
Planning reference
2660834
Application type
Permission
Applicant
Patricks Rock Solar Ltd
Agent
Niamh McHugh

Numbers and dates

Homes
~17estimated from the application
Floor area
255 m²per planning documents
Project type
Temporary/event
Received
28 Aug 2026
Decision due
29 Nov 2026

Outlook

What happens next

The council's decision is due on 29 Nov 2026. Building work can only follow a grant of permission.

Work packages named so far

  • Solar PVNamed in the planning documents
  • GroundworksNamed in the planning documents

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660834 on eplanning.ie: drawings, reports and the decision.Open the council's file
  • From the planning documentsRead from Application Form - Part A in the council's file.
    Floor area
    255 m² (per planning documents)
    Site area
    151 ha
    Applicant
    Patricks Rock Solar Ltd.
    Scope
    Construction of a solar photovoltaic energy development on 151 hectares, including solar panels, transformers, compounds, cabling, fencing, CCTV, entrance upgrades, internal tracks, landscaping, and associated works.
    Solar PV
    “erection of solar panels on ground-mounted galvanised steel frames”
    Groundworks
    “internal site access tracks”

Reviewed build intelligence

What the documents establish

Government document review

A new solar application was received 28 August 2026 and acknowledged on 1 September. The 17 units in the description are transformers, not homes. Separate future grid and substation permission is explicitly outside this application.

3 official documents inspected · Checked 2026-09-07 · Official file index

Council acknowledges the new solar application; permission is not established

Application and requested lifespan, not a granted construction or operating period

What the evidence says
The council acknowledgement dated 1 September records receipt on 28 August of a solar proposal described as 151 hectares with 17 transformer units and associated compounds and access works. It expressly leaves validity subject to the site-notice requirements. The application seeks a ten-year permission period and forty-year operating life from commissioning.

Why it may matter — interpretation
Solar and enabling-work suppliers can assess an early planning proposal while keeping authorisation and delivery timing open.

What is not established
Planning decision, final permission, site-notice inspection outcome, grid approval and commencement are not established.

Inspect the evidence

Council acknowledgement of application receipt · p.1
Acknowledgement 1 September; received 28 August; 151 hectares and 17 transformers · Issued 2026-09-01 · Acknowledgement dated 1 September; received 28 August; validity subject to site notice inspection · Checked 2026-09-07

Acknowledgement 1 September; received 28 August; 151 hectares and 17 transformers

Council acknowledgement of application receipt · p.2
Validity subject to site-notice compliance · Issued 2026-09-01 · Acknowledgement dated 1 September; received 28 August; validity subject to site notice inspection · Checked 2026-09-07

Validity subject to site-notice compliance

Application cover letter and infrastructure scope · p.1
Ten-year permission sought; forty-year life from commissioning · Issued 2026-08-27 · Cover letter 27 August, received 28 August · Checked 2026-09-07

Ten-year permission sought; forty-year life from commissioning

August drawings define indicative PV geometry and tested piling depth

August planning design; indicative geometry rather than selected final equipment

What the evidence says
The revised panel arrangement shows fixed tables up to 3.2 m high, 10 to 30 degree tilt and at least 800 mm ground clearance. It locates string inverters at the support structure and leaves ramming depth to site tests, with a typical 1.5 to 2.5 m range. The transformer drawing shows an indicative enclosure and explicitly allows detailed-design and procurement variation.

Why it may matter — interpretation
Ground-mount, piling and electrical contractors need terrain and ground investigations coordinated with final equipment procurement.

What is not established
Final module and inverter selections, installed MW capacity, pile-test results and transformer electrical ratings are not established.

Inspect the evidence

Planning drawings pack, part 2 of 4 · p.2
MCS-205 rev C: height, tilt, clearance, inverter and ramming-test note · Issued August 2026 (month only) · PDF p1 MCS-030 rev D 25 August; p2 MCS-205 rev C 25 August; p4 MCS-217 rev C 14 August; p12 crossing C-0521 P01 17 August, preliminary S0; received 28 August · Checked 2026-09-07

MCS-205 rev C: height, tilt, clearance, inverter and ramming-test note

Planning drawings pack, part 2 of 4 · p.4
MCS-217 rev C: indicative transformer enclosure and detailed-design caveat · Issued August 2026 (month only) · PDF p1 MCS-030 rev D 25 August; p2 MCS-205 rev C 25 August; p4 MCS-217 rev C 14 August; p12 crossing C-0521 P01 17 August, preliminary S0; received 28 August · Checked 2026-09-07

MCS-217 rev C: indicative transformer enclosure and detailed-design caveat

Grid connection and substation require a separate future application

Current solar-farm scope distinguished from future grid infrastructure

What the evidence says
The cover letter explicitly reserves the grid connection and onsite substation compound for a later application. The operations-compound drawing labels a distinct area for an onsite substation and IPP building subject to future planning, beside the proposed welfare and storage facilities.

Why it may matter — interpretation
Electrical and civil teams should avoid treating the solar planning pack as approval of the export connection or future substation works.

What is not established
A verified later grid application, grid-connection agreement, substation permission and export capacity are not established.

Inspect the evidence

Application cover letter and infrastructure scope · p.2
Grid connection and onsite substation subject to separate future application · Issued 2026-08-27 · Cover letter 27 August, received 28 August · Checked 2026-09-07

Grid connection and onsite substation subject to separate future application

Planning drawings pack, part 2 of 4 · p.1
MCS-030 rev D: future substation / IPP area versus operations compound · Issued August 2026 (month only) · PDF p1 MCS-030 rev D 25 August; p2 MCS-205 rev C 25 August; p4 MCS-217 rev C 14 August; p12 crossing C-0521 P01 17 August, preliminary S0; received 28 August · Checked 2026-09-07

MCS-030 rev D: future substation / IPP area versus operations compound

The clearspan watercourse crossing is expressly preliminary

Submitted preliminary crossing detail, not an approved construction design

What the evidence says
The crossing drawing proposes a clearspan structure with precast abutments combined with in-situ foundations. It requires the crossing specification to be finalised with the OPW during the Section 50 process and refers to mitigation agreed with fisheries and wildlife authorities. The sheet is marked preliminary, S0 initial status or work in progress.

Why it may matter — interpretation
Bridge, civil and ecology teams need the regulatory and engineering agreement resolved before ordering the crossing or carrying out works at the channel.

What is not established
Section 50 approval, final structural dimensions, hydraulic acceptance and completed mitigation agreements are not established.

Inspect the evidence

Planning drawings pack, part 2 of 4 · p.12
C-0521 P01: clearspan crossing; preliminary S0; OPW specification to be finalised · Issued August 2026 (month only) · PDF p1 MCS-030 rev D 25 August; p2 MCS-205 rev C 25 August; p4 MCS-217 rev C 14 August; p12 crossing C-0521 P01 17 August, preliminary S0; received 28 August · Checked 2026-09-07

C-0521 P01: clearspan crossing; preliminary S0; OPW specification to be finalised
Remaining document questions
  • Have the site-notice validation, planning decision, separate grid application and final crossing specification progressed?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

How we know this

From the Tipperary County Council planning register, checked 22 Oct 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Cashel

Get alerts for CashelFree. We email you when new applications appear.

Free email alerts

Get new Cashel projects by email

New applications, decisions and site starts in Cashel, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options