Energy · Co. Waterford
Cooltubbrid West, Kilmacthomas, Co. Waterford
Granted 14 Sep 2023 (final grant issued 20 Oct 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Kilmacthomas by email
Key facts
- Planning application 2360317 at Cooltubbrid West, Kilmacthomas, Co. Waterford: Extension of the operational lifespan of a solar farm permitted…
- It was received by Waterford City and County Council on 21 Jul 2023.
- Status: Granted 14 Sep 2023 (final grant issued 20 Oct 2023).
Source: the Waterford City and County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Kilmacthomas · Planning applications in Co. Waterford
Council register
The council's register shows: Granted on 14 Sep 2023.
Search the Waterford planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Extension of the operational lifespan of a solar farm permitted…
the extension of the operational lifespan of a solar farm permitted by An Bord Pleanála under Ref. ABP PL24.248413 (Waterford City and County Council Planning Ref 17/96) from 25 No. years as permitted (by reason of Condition No.3 of permission Ref. ABP PL24.248413) to 40 No. years.
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Kilmacthomas, Co. Waterford Map
- Planning reference
- 2360317
Numbers and dates
- Project type
- Energy
- Received
- 21 Jul 2023
- Decision to grant
- 14 Sep 2023
- Final grant
- 20 Oct 2023
- Site start notified
- 13 May 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier application 1796 for this site: refused 6 Apr 2017.
proposed works will include a 4.2MVA solar farm comprising photovoltaic panels on ground mounted frames, four single storey… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Documents and evidence
Check the record
- Council planning fileThe application file 2360317 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Waterford City and County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 13 May 2024Notice filed · Single storey solar farm substation control building and associated worksView the site start
- Completion certificate recordedRecorded in May 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.