~24 dwellings, Tigroe, Kilmeaden, County Waterford
for 10 year planning permission for the development which will consist of the construction of a Battery Energy Storage System (BESS) development on a 2.49 hectare site consisting of:- I. The installation of 48 No. BESS Modules on concrete plinths; II. 24 No. MV Skid Units on concrete plinths; III. 1No. 110kV Transformer and...
The public decision state is shown, but conditions and later amendments can still change delivery scope.
Package signals below are limited to wording in the public application record.
No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.
Opportunity & supplier intelligence
What is known, and what may happen next
Timing is a planning-stage outlook, not a tender, award, contractor appointment, supplier appointment or guaranteed procurement date.
A planning decision is recorded and no linked commencement is indexed. Conditions, procurement and start timing remain unconfirmed.
Decision date 3 Sep 2026. / Confidence: LowDecision date 3 Sep 2026.
No commencement indexed / This is an index state, not proof that no works have started.
Source limited29 drawing entries are present in the official document inventory.
- Planning Drawing List - Other Assessments
- Traffic Management Plan - Other Assessments
- Construction and Environmental Management Plan - Other Assessments
Confirmed scope
Confirmed application scope
Construction of a Battery Energy Storage System (BESS) development on a 2.49 hectare site comprising 48 BESS modules, 24 MV skid units, a 110kV transformer, a modular control building, security fencing, cameras and lighting, a new site entrance, access tracks, electrical cabling, and landscaping.
Open scope evidenceNamed firms
Public source roles
- Tigroe Energy Limited
- Applicant / promoter named in an official planning document
- Document role only; current development or appointment status is not confirmed.
- Tigroe Energy Ltd
- Applicant / promoter on the public planning record
- Application role only; current development or appointment status is not confirmed.
Evidence-backed work packages
Explicit source signals only
Groundworks
construction of new access tracks
Confidence & provenance 1 official source
- Authority
- Waterford City and County Council
- Exact reference
- 2560872
- Evidence reviewed
- 16 Sep 2026
- Confidence
- Document-derived
Facts come from the indexed public planning record and any bounded structured document evidence. No request-time official fetch, tender, award or appointment inference is used.
What the public record evidences
Large residential - 24 dwellings
The public application record identifies 24 dwellings in the submitted planning scope.
Only source-supported scope signals are shown; generic trade padding is omitted.
More actions
Named source parties
- Promoter
- Tigroe Energy Ltd
- Planning agent
- Barry McGinn
- Agent address
- 30 Drumcondra Road Upper Drumcondra Dublin 9 D09 FT7K
- Builder / developer
- Tigroe Energy Limited
Facts extracted from official planning documents
- Floor area (per planning documents)
- 22 m²
- Site area
- 2.49 ha
- Applicant / promoter
- Tigroe Energy Limited
- Scope
- Construction of a Battery Energy Storage System (BESS) development on a 2.49 hectare site comprising 48 BESS modules, 24 MV skid units, a 110kV transformer, a modular control building, security fencing, cameras and lighting, a new site entrance, access tracks, electrical cabling, and landscaping.
Facts only; drawings and document packs are not republished.
Source: Application Form - Part A, Waterford City and County Council planning file
Open official planning document
More Waterford planning activity
These are county discovery links, not claimed relationships to this application.
Application text
for 10 year planning permission for the development which will consist of the construction of a Battery Energy Storage System (BESS) development on a 2.49 hectare site consisting of:- I. The installation of 48 No. BESS Modules on concrete plinths; II. 24 No. MV Skid Units on concrete plinths; III. 1No. 110kV Transformer and associated switchgear and electrical equipment; IV. 1 No. Modular Customer Control Building; V. Erection of 2.6m high security fencing around the site; VI. Installation of pole-mounted security cameras and lighting; VII. Construction of 1 No. new permanent site entrance; VIII. Construction of new access tracks; IX. Installation of electrical cabling; X. Landscaping and reinstatement works; and XI. All associated ancillary development.
Application to site progress
-
Applied 5 Dec 2025 2560872
-
Decision Conditional 3 Sep 2026
-
Appeal No appeal indexed No public appeal record is indexed against this application.
-
Commenced No commencement indexed No reliable public commencement record is indexed against this permission.
-
Completed Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Source, scope and limits
Application description and scale 2560872
for 10 year planning permission for the development which will consist of the construction of a Battery Energy Storage System (BESS) development on a 2.49 hectare site consisting of:- I. The installation of 48 No. BESS Modules on concrete plinths; II. 24 No. MV Skid Units on concrete plinths; III. 1No. 110kV Transformer and associated switchgear and electrical equipment; IV. 1 No. Modular Customer Control Building; V. Erection of 2.6m high security fencing around the site; VI. Installation of pole-mounted security cameras and lighting; VII. Construction of 1 No. new permanent site entrance; VIII. Construction of new access tracks; IX. Installation of electrical cabling; X. Landscaping and reinstatement works; and XI. All associated ancillary development.
Open official record