Large residential · Co. Westmeath
Lands at Boreen Bradach, Kinnegad, Co. Westmeath.
Granted 3 Oct 2025
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 11 Jun 2026. The details below are as they were then. The council's register has the current status.
Search the Westmeath planning registerCurrent planning applications in Kinnegad
What and where
~129 homes
a Large-Scale Residential Development (LRD) at this site of c.4.279 ha (gross) at Boreen Bradach, Kinnegad, Co. Westmeath. The main development site is bounded by Boreen Bradach Road (L-5014)/Bun Daire estate to the east/north-east, St Etchen’s National School to the west and St Etchen’s Court to the south. The proposed development will comprise a residential scheme of 129 no. houses along with childcare facility (c.261.3 sq.m). The development will include 2 no. 1-bed houses, 11 no. 2-bed houses, 97 no. 3-bed houses and 19 no. 4-bed houses, ranging in height from one to two storey and including detached, semi-detached and terraced units. Provision of vehicular, pedestrian/cyclist access from the L-5014 (Boreen Bradach Road) and associated upgrades to the local road. All associated site development works, including 263 no. car parking spaces (including 30 no. EV spaces), 330 no. cycle parking spaces. Provision of public and private open spaces, landscaping, boundary treatments, waste management areas, and services provision (including 2 no. ESB substations). All associated works required to enable this development including connection to the Uisce Eireann network
- Location
- Kinnegad, Co. Westmeath Map
- Council
- Westmeath County Council
- Planning reference
- 2560234
- Applicant
- Jh Kinnie Ltd
- Agent
- McGill Planning Ltd
Key facts
- Homes
- ~129estimated from the application
- Floor area
- 14,752 m²
- Estimated construction value
- €22m to €29mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 13 May 2025
- Granted
- 3 Oct 2025
- Site start
- 10 Apr 2026
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2560234 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Westmeath County Council planning register, as last seen on 11 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 10 Apr 2026Work started · 127 no. Two Storey dwellings adn associated site works
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.