Infrastructure · Co. Wicklow
Ballinaclogh, Ballynabarny, & Ballybeg, Co. Wicklow
Granted 6 Jun 2025 (final grant issued 15 Jul 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Wicklow by email
Key facts
- Planning application 2560311 at Ballinaclogh, Ballynabarny, & Ballybeg, Co. Wicklow: Development of grid connection infrastructure.
- It was received by Wicklow County Council on 24 Apr 2025.
- Status: Granted 6 Jun 2025 (final grant issued 15 Jul 2025).
- Work was due to start on 18 Jun 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Wicklow County Council planning register, as last seen on 5 Oct 2026. Open the council's file
Council register
The council's register shows: Granted on 6 Jun 2025.
Search the Wicklow planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Development of grid connection infrastructure
the development of grid connection infrastructure comprising the laying of ca. 3.3 kilometres (3,300 metres) of Medium Voltage underground electricity cables and associated infrastructure substantially under public roads and private lands to connect the solar photovoltaic (‘PV’) energy development on lands at Ballinaclough, Rathnew, Country Wicklow (approved under Register Reference 161380) to a new Medium Voltage electricity substation and to a new joint slab box on private land near L95113 road in, or in the vicinity of the townlands of Ballinaclogh, Ballynabarny and Ballybeg, County Wicklow
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Ballybeg, Co. Wicklow Map
- Council
- Wicklow County Council
- Planning reference
- 2560311
Numbers and dates
- Project type
- Infrastructure
- Received
- 24 Apr 2025
- Decision to grant
- 6 Jun 2025
- Final grant
- 15 Jul 2025
- Site start notified
- 18 Jun 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2560311 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Wicklow County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 18 Jun 2026Notice filed · Single storey substation control building of traditional blockwork construction, forming...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.