Barnahely, Ringaskiddy, Co. Cork
Retention Permission for provision of an agricultural entrance and alterations to public lighting and access road to Warrens Court as granted planning permission under Planning Reg. Nos. 19/4640 and...
Co. Cork
15 planning applications · 73 site starts · latest 3 Nov 2026
Source: each council's planning register. Every record below links to its own page and to the council's file.
Newest first
Retention Permission for provision of an agricultural entrance and alterations to public lighting and access road to Warrens Court as granted planning permission under Planning Reg. Nos. 19/4640 and...
The renewable energy development will consist of the construction of a wind turbine with a hub height of up to 100m, a rotor radius of up to 70m, and an overall height from existing ground level to tip...
The development shall include the construction of a new two-storey electrical substation building, access platforms and stairs, foundations and ground works, electrical ducting and associated works. The...
Proposed prefabricated manufacturing building. extending from an existing prefabricated building at Barnahely, Ringaskiddy, Co. Cork
Planning permission to construct a new dwelling house.
In Ringaskiddy
In Ringaskiddy
Dated since 1 Nov
Newest record date
44 of 88 · then Extension, Alteration
Earlier records
The proposed development will consist of: 1. Permission for temporary retention for a period of 5 years for the use of 2 No. existing single-storey modular office buildings (Buildings Nos. 8 and 9), each...
Planning Permission for the installation of Solar PV Panels to be mounted on the rooftop of an existing production building and all associated ancillary infrastructure. PV Panels will not extend above...
1) Permission for retention of the following, a) modifications to the elevations, b) additional production floor area of i) 32 square metres at ground floor level, ii) 22.1 square metres at ground floor...
Planning permission for the construction of a single storey Electrical Room extension over service void on the roof of the existing Blower House Building including external access stairs and ladders and...
Planning permission for works to upgrade the existing Waste Water Treatment Plant to the south of the existing production facility, including the following: a) the demolition of an existing control...
Permission for 1 No. prefabricated single storey building for manufacturing installed to the north east of the site and with link corridors to be provided from proposed building to existing buildings...
Permission for retention of: a) Detached garage structure in the rear yard of our property with a self-contained one-bedroom apartment at attic floor level over for use as ancillary residential...
Construction of a dwelling house, site entrance, domestic garage and all associated site works
Permission for the construction of a dwellinghouse and associated site works.
Permission for Retention of alterations to elevations of 1 no. dwelling (no.4) as granted planning permission under Planning Reg No. 19/6785.
Retention Permission for alterations to floorplans & elevations of 3 no. dwellings (No's. 13, 23, & 30) and Retention Permission for alterations to elevations of 14 no. dwellings...
Construction of a new Single storey steel framed structure for a medium voltage and low voltage (MV &LV) electrical sub-station with 2 no. single storey over service void building units, at J&J...
Permission for 1) change of use of 5 no. existing permitted storage tanks on site from the storage of molasses to the storage and distribution of HVO (Hydrogenated Vegetable Oil) fuel, 2) raising of bund...
construction of dwelling and associated site works
Permission for the construction of 1) a new three-level extension to the north elevation of the existing production building 02, 2) a new five-level extension to the eastern elevation of the existing...
Janssen Sciences Ireland UC - two storey autoclaves and washers extension to existing production building
New single storey waste water treatment plant amenities building
1) The demolition of part section of the existing laboratory and existing carpark spaces, 2) The construction of a new four storey laboratory expansion to the south of the existing site buildings, new...
Janssen Sciences Ireland UC - BioCore Restaurant - Material alterations and 2 No. single storey extensions to the existing canteen.
The proposed development consists of a new single-storey Electrical building & all Ancillary Site Works
The proposed development consists of a new single-storey Electrical building & all Ancillary Site Works
Demolition of existing single storey derelict house and construction of two storey dwelling house and associated siteworks
Construction of 30no. houses at Barnahely, Ringaskiddy, Co. Cork. [House Nos 1-30]
Construction of 4no. houses at Barnahely, Ringaskiddy, Co. Cork. [House Nos 1-4]
Construction of a dwelling house and all associated services
An Loch Beag Clós, Ringaskiddy: Demolition of demountable residential accommodation units and the construction of 15 no. 2, 3 and 4 bedroomed townhouses (Nos. 1-15) across three blocks and ancillary site...
The Proposed Development consists of the construction of a Guardhouse and Associated Works
the construction of a two storey fish processing factory building and associated works
Works will include the construction of a new electrical building, emergency back up electrical power generation and associated containment bund, screening and associated site development works.
The construction of new single-storey building that is to house two Electrical rooms. The building is to be on a split level site and include all ancillary site development works.
Construction of 18 No. Two Storey Dwellings at Barnahely, Ringaskiddy, Co. Cork. [House Nos 13-30]
Pfizer Ireland Pharmaceuticals - OSP4 Rack Room Extension - The proposed works consist of the construction of a new two-storey extension to the Eastern side of the building.
The proposed development consists of a small single storey building which is to be used as an MCC electrical control room. The building is to be located on the site of the R&H Hall bulk storage facility...
The construction of a single storey Modular Building (Welfare Facility) located in the existing Recycling Centre area
Construction of 12 No. Two Storey Dwellings at Barnahely, Ringaskiddy, Co. Cork. [House Nos 1-12]
The proposed development involves the stabilisation, reconstruction and improvement of fire damaged bulk storage warehouse and associated plant and equipment at Ringaskiddy Deepwater Berth, Ballybricken...
The erection of 1 No. temporary single storey modular building. The temporary building will be required for a maximum period of three years. The temporary building will comprise of a gowning and locker...
Janssen BioCork 3.2 Expansion - six extensions to existing building
The proposed development consists of a new 2 Storey Water Treatment and Electrical Building at Pfizer Ireland Pharmaceuticals. API Plant, Ringaskiddy, Co Cork
Construction of 2 No. Dwellings and all ancillary site development works.
Renovations & Alterations to existing Community Hall
Construction of new single storey detached dwelling of masonry construction and associated siteworks
Material alteration to part of first floor of existing two storey office building at Zenith Technologies Ltd., Portgate Business Park, Ringaskiddy, Co. Cork.
Pfizer RCMF Project - construction of three new buildings: (1) RCMF Building; (2) Electrical Building; (3) Drum Store.
Construction of a two-storey building consisting of ground floor laboratory, first floor office with ancillary staff facilities and a pedestrian link to existing building at Barnahely, Ringaskiddy, Co...
Fit out of additional office space within the Ferry Terminal Building and upgrade of the existing kitchen facility.
Production fallow space fitout.
The construction of a two storey extension to existing industrial building to provide an MCC room at ground floor level and a rack room at first floor level to OSP4 Finished Goods Building
Opt Out- Construction of a new dwelling house
Alterations and extensions to an existing dwelling, decommissioning of an existing septic tank, a new connection to the mains foul sewer on the public road and all other associated site works
Depuy - Process Area consists of the construction of 1 no. single storey steel framed Building
Construction of a new straddle carrier crane maintenance building and associated workshop and stores spaces.
Customs Inspection Building for Port of Cork - The project is to consist of the construction of a New Single Storey Building to be used by Customs for the Inspection of vehicles that intend to use the...
Pfizer Ringaskiddy - ES2020 Carbon SS EOL Device - Construction of new 3 storey Services Building and Associated Site Works
2 Storey Extension to Warehouse
Proposed Four Storey Extension to the South Elevation of the Existing Building along with varying vertical extensions to the West & East Elevations of the Existing Building complete with single storey...
Construction of new Dwelling House with waste water treatment system and ancillary site works
Substation 2, Single Storey Electrical Building
Two Storey Electrical room extension to existing Laboratories and Offices Building.
Janssen Sciences Ireland - BioCork 2 Project - WWTP MCC Building: Construction of a new single-storey building (10m x 5m on plan) for electrical equipment associated with the site Waste Water Treatment...
Erection of 1 bungalow and domestic garage
Opt Out - Construction of a new dwelling house
Construction of a Sub-station adjacent to the existing Utilities Building at their production facility in Ringaskiddy, Co Cork
The works comprise of an upgrade to an existing warehouse and the installation of an AHU and associated support platform at roof level on an adjacent building at an existing production facility.
OSP4, Pfizer API Plant, Ringaskiddy - Construction of a Single Storey extension to Finished Goods Building to provide Maintenance Area
Construction of one and a half storey house previously granted under planning ref: 10/4748
Works will include the construction of a new 2 storey L- shaped building to the east of the existing Manufacturing Building. The new building will be connected to the existing Manufacturing Building via...
Phase 3 of 3: Construction of a 4 storey extension to the north east corner of the existing manufacturing building. The works will also include associated site development works.
An extension to the existing biomedicines manufacturing facility including a new production building, 3 no. warehouse extensions, an administration/laboratory building, a cafeteria extension, additional...
Gymnasium Development at Shamrocks GAA Club, Shanbally, Ringaskiddy, Co. Cork.
Two-storey extension to an existing Laboratory building at Pfizer production facility at Ballintaggart and Ballybricken townlands.
Construction of 4 no. single-storey, modular office buildings, 1 no. firewater pumphouse and all associated utilities, drainage and access.
Material Alterations to existing unit and Change of Use from Light Industrial to Office of Part Ground Floor at Zenith Ltd, Portgate Business Park, Ringaskiddy, Co. Cork
Construction of extension to existing bulk feed facility consisting 4 No silo bins with overhead enclosed conveyor system to connect to the existing building on the west side of the site, construction of...
Construction of a Golf Course Maintenance Equipment Store at Shanbally, Ballintaggart & Ballybricken Townlands, Ringaskiddy, Co. Cork.
Extension of the Ground floor area of the existing PB1A building. Additional works are also required on the Ground floor and First floor of the existing building.
Construction of a 403m2 Single Storey extension to the existing Administrattion Building at Recordati Ireland, Raheens East, Ringaskiddy Co Cork. The works include alterations to the existing car park...
Warehouse extension to western elevation of existing warehouse
Extension to the existing plant room at third floor level of the existing Administration Building.
Construction of 2no. Single Storey Prefabricated Temporary Buildings for ancillary office accommodation
The construction of a private dwelling and associated site works
The erection of a single storey prefabricated temporary building at Janssen Biologics (Ireland)Ringaskidd y, Co. Cork
New Modular Building - Temporary Office Accommodation with link corridor to existing building
Council
Nearby
Explore
Last 12 months
1 refusal in Ringaskiddy in the last 12 months.
Ballintaggart, Shanbally, Ringaskiddy, Co. Cork. Transport/access
The proposed development would be considered premature pending the completion of the M28 Cork to Ringaskiddy Project and would result in the intensification of an existing direct access to a national road which would… Refused 23 Feb 2026 · 25/6891Quick answers