Connected planning records

Commercial new build, 302, Brownsbarn Drive, Citywest Business Campus, Dublin... - Planning Application SD26A/0084W

South Dublin County Council · SD26A0084W · Dublin

Latest linked evidence

Notified commencement · 2026-08-14

The proposed development shall consist of the construction of a new industrial building located at the northern end of the site. The proposed building, while physically separate from the existing structure, shall form part of the overall premises on site as an ancillary structure and shall be occupied in conjunction with the existing building. The proposed building shall have an overall footprint of 739 sq.m and shall be constructed with a steel portal frame, incorporating an insulated composite panel roof system and horizontally spanning metal wall panels. The parapet height shall be set at 110.65m O.D., approximately 10.05m above existing yard level and 0.35m below the level of the existing building. The building shall include a roller shutter door (6.0m x 5.0m) on the western elevation and a roller shutter door (4.85m x 5.0m) on the southern elevation, together with various personnel and fire access doors around the perimeter. Access shall be provided via improved yards and hardstanding's, within which Suds features shall be incorporated

Indexed observation: Granted. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

Final permission issued on 19 August for a 739 m² ancillary industrial building within the existing Citywest premises. The reviewed documents do not establish commencement or completion.

3 official documents inspected · Checked 2026-09-07 · Official file index

Final grant defines a 739 m² steel-frame industrial building

Granted industrial building and envelope description

What the evidence says
The 19 August final grant describes a physically separate building ancillary to the existing premises, with a steel portal frame, insulated composite roof panels and horizontal metal wall panels. It sets the parapet at 110.65 m OD, about 10.05 m above the yard, and specifies west and south roller doors.

Why it may matter — interpretation
Steelwork, cladding and door suppliers have a defined planning-stage package to qualify against construction details.

What is not established
Fabricator appointment, panel product selection, manufacture and installation are not established.

Inspect the evidence

Final grant including amended contribution condition · p.1
Final Grant 19-Aug-2026; 739 sq.m; steel portal frame · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Final Grant 19-Aug-2026; 739 sq.m; steel portal frame

Tree-pit drainage needs an agreed slope and inflow detail

Pre-commencement drainage condition and submitted response

What the evidence says
Condition 2 requires revised plan and cross sections showing how hardstanding runoff reaches tree pits, replacing the proposed 1:2 side slope with 1:3 or 1:4, or agreeing an alternative with Water Services. The July revision B submission shows two tree pits and runoff inlets; its presence does not prove council agreement.

Why it may matter — interpretation
Civil and landscape teams need the approved slope, inflow and overflow interface before constructing the tree-pit SuDS.

What is not established
Written acceptance of condition 2, installed attenuation and as-built drainage performance were not reviewed.

Inspect the evidence

Final grant including amended contribution condition · p.2
Condition 2: slope profile of 1:3 or 1:4 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Condition 2: slope profile of 1:3 or 1:4

Submitted SuDS plan and tree-pit details · p.1
PROPOSED SUDS PLAN AND TREE PIT DETAILS; revision B · Issued 2026-07-20 · 25039-20-DR-0025 revision B; revised for planning 20 July; special-version stamp refers to original signatures · Checked 2026-09-07

PROPOSED SUDS PLAN AND TREE PIT DETAILS; revision B

All surface parking needs EV ducting; 20% needs initial chargers

Pre-commencement roads and electrical conditions

What the evidence says
Condition 8 requires ducting and termination points at all surface parking spaces and charging points at 20% initially. The EV design and signage, public lighting design and construction management plan require written agreement before development starts.

Why it may matter — interpretation
Electrical contractors need the agreed parking count and layout to turn the percentages into equipment quantities and cable routes.

What is not established
Charger counts, equipment make, agreed compliance details and installed charging infrastructure are not established.

Inspect the evidence

Final grant including amended contribution condition · p.3
Condition 8: 100% ducting; 20% charging points initially · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Condition 8: 100% ducting; 20% charging points initially

Crane use and vegetation protection affect the construction programme

Conditions governing site mobilisation and lifting

What the evidence says
Condition 7 requires crane operations to be coordinated with Air Corps air-traffic services at least 28 days before use. Conditions 5 and 6 require green-infrastructure details, hedgerow protection and an arboricultural method statement, with protection implemented before site works.

Why it may matter — interpretation
Steel erection and siteworks programmes need to allow for aviation coordination and vegetation-protection arrangements.

What is not established
Crane coordination, agreed protection plans and mobilisation are not established.

Inspect the evidence

Final grant including amended contribution condition · p.2
Conditions 5 and 6 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Conditions 5 and 6

Final grant including amended contribution condition · p.3
Condition 7: no later than 28 days before use · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Condition 7: no later than 28 days before use

The amended condition uses 739 m² rather than the earlier 1,858 m² error

Final grant incorporates the July condition correction

What the evidence says
The final grant reproduces condition 18 and then expressly replaces it with the 17 July amendment: the contribution is 88,325.28 euro rather than the earlier 222,068.16 euro. This is a correction to the contribution calculation, not a larger industrial-building scope.

Why it may matter — interpretation
Commercial review should use the amended amount and the 739 m² development description when checking the permission.

What is not established
Payment, any later index adjustment and satisfaction of the financial condition are not established.

Inspect the evidence

Final grant including amended contribution condition · p.5
Earlier condition 18: 222,068.16 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Earlier condition 18: 222,068.16

Final grant including amended contribution condition · p.6
Condition 18 was amended by PR/0805/26 on 17/07/2026: 88,325.28 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07

Condition 18 was amended by PR/0805/26 on 17/07/2026: 88,325.28

Amended executive order correcting the contribution · p.2
Contribution corrected from 1858 m2 to 739 m2 · Issued 2026-07-17 · PR/0805/26 signed 17 July 2026 · Checked 2026-09-07

Contribution corrected from 1858 m2 to 739 m2
Remaining document questions
  • Has the council agreed the pre-commencement drainage, EV, lighting and vegetation-protection submissions?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

Source history

Timeline

  1. Planning application received

    SD26A0084W

    Official source

  2. Planning decision

    SD26A0084W

    Permission granted

    Official source

  3. Notified commencement

    Commencement notice

    The proposed development shall consist of the construction of a new industrial building located at the northern end of the site. The proposed building, while physically separate from the existing structure, shall form part of the overall premises on site as an ancillary structure and shall be occupied in conjunction with the existing building. The proposed building shall have an overall footprint of 739 sq.m and shall be constructed with a steel portal frame, incorporating an insulated composite panel roof system and horizontally spanning metal wall panels. The parapet height shall be set at 110.65m O.D., approximately 10.05m above existing yard level and 0.35m below the level of the existing building. The building shall include a roller shutter door (6.0m x 5.0m) on the western elevation and a roller shutter door (4.85m x 5.0m) on the southern elevation, together with various personnel and fire access doors around the perimeter. Access shall be provided via improved yards and hardstanding's, within which Suds features shall be incorporated

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.