Save this project to account
Connected planning records

Planning case 320919

Dublin City Council · 320919 · Dublin City, Dublin

Latest linked evidence

Notified commencement · 2021-05-14

Construction of Buildings 2 & 6 as part of the Grand Canal Harbour Mixed-Use Residential Development at Grand Canal Place, Dublin 8. (Building 2 @ 10 Storeys above ground and Building 6 @ 6 Storeys above ground). (These works are subsequent to works covered under commencement notices,, & 7DN Sub.No.8460876) (It is further noted the crèche in Block 2 and the medical area at ground/first in Block 6 will be completed to shell only at completion of the Buildings. The fit-out of the the crèche in Block 2 and the medical area at ground/first in Block 6 will be subject to their own separate CN, BCAR Process and CCC).

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    320919

  2. Planning decision

    320919

    Permission granted

  3. Grant date recorded

    320919

  4. Notified commencement

    Commencement notice

    Grand Canal Harbour Block 5: Extension & material alteration to an existing four- storey warehouse building (a Protected Structure reference no. 3275), the construction of a new three-storey extension adjoining the warehouse building to the west, and associated site works. All to include Retail Unit, Café, Co- Working Spaces, Medical Consultant Services & Artist Studio. These works are subsequent to works already commenced under commencement notices &. Note: The retail unit, café, co-working spaces, medical consultant services & artist studio will be completed to shell only at completion of the Building. The ?t-out of the retail unit, café, co- working spaces, medical consultant services & artist studio will be subject to their own separate CN, BCAR Process and CCC).

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of Buildings 1 & 3/4 as part of the Grand Canal Harbour Mixed-Use Residential Development at Grand Canal Place, Dublin 8. (Building 1 @ 10 Storeys above ground and Building 3/4 @ 12 Storeys above ground). (These works are subsequent to commencement notices, & ) (It is further noted the Retail Area and Café/Bar/Restaurant at Ground Floor in Building 1 and the Bar/Restaurant, Retail Area and the two office spaces at Ground/First floor in Building 3/4 will be completed to shell only at completion of the Buildings. The fit-out of the Retail Area and Café/Bar/Restaurant at Ground Floor in Building 1 and the Bar/Restaurant, Retail Area and the two office spaces at Ground/First floor in Building 3/4 will be subject to their own separate CN, BCAR Process and CCC).

    262 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of Buildings 2 & 6 as part of the Grand Canal Harbour Mixed-Use Residential Development at Grand Canal Place, Dublin 8. (Building 2 @ 10 Storeys above ground and Building 6 @ 6 Storeys above ground). (These works are subsequent to works covered under commencement notices,, & 7DN Sub.No.8460876) (It is further noted the crèche in Block 2 and the medical area at ground/first in Block 6 will be completed to shell only at completion of the Buildings. The fit-out of the the crèche in Block 2 and the medical area at ground/first in Block 6 will be subject to their own separate CN, BCAR Process and CCC).

    281 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.