Connected planning records

Planning case 2660536

Kerry County Council · 2660536

Latest linked evidence

Planning decision · 2026-08-05

2660536 · Conditional permission

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What is being built

Government document review

W34 appeal324591 concerns Kerry2660536 and259 proposed dwellings. The NIS revision02 dated2June2026 retains alternative surface-water outfalls and specific habitat-related lighting requirements; appeal pending.

1 official documents inspected · Checked 2026-09-05 · Official file index

The NIS retains two outfall options

Proposed options; selection not established · Proposed drainage for the259-dwelling Countess Road scheme

What the evidence says
Both options use the on-site SuDS treatment train and restrict runoff to28.5L/s. Preferred Option1 uses the Countess Road public network via Countess Grove; Option2 uses an existing600mm public pipe toward the River Flesk. The report explicitly leaves Option1’s downstream treatment pathway uncertain.

Proposed drainage for the259-dwelling Countess Road scheme Downstream route uncertainty expressly retained by the NIS

Why it may matter — interpretation
Interpretation for drainage engineers: the unresolved outfall pathway is a concrete approval/design question affecting connection works.

What is not established
No final outfall selection, accepted connection, installed system or available contract is proven. Obtain the final drainage agreement; do not present the preferred option as selected.

Inspect the evidence

Countess Road LRD Natura Impact Statement · p.32
Inspected PDF page 32 · Issued 2026-06-02 · WS0950_CountessRoad_NIS_FINAL_02; replaces revisions00/01; received11June2026 · Checked 2026-09-05

28.5 l/s

Lighting is pulled back from sensitive site boundaries

Proposed in the inspected application · June2026 proposed Countess Road lighting mitigation; not a product schedule

What the evidence says
The NIS retains dark areas along eastern and south-western boundaries and pulls lighting back from the southern boundary. It describes proposed private downlighters with1.0lx spill onto footpaths and minimal spill beyond.

June2026 proposed Countess Road lighting mitigation; not a product schedule

Why it may matter — interpretation
Interpretation for lighting designers and ecologists: boundary spill and dark-route requirements constrain the coordinated external-lighting layout.

What is not established
Fitting brand, count, final approved photometry and installed light levels are not established. Inspect the illumination contour drawing and eventual appeal conditions.

Inspect the evidence

Countess Road LRD Natura Impact Statement · p.62
Inspected PDF page 62 · Issued 2026-06-02 · WS0950_CountessRoad_NIS_FINAL_02; replaces revisions00/01; received11June2026 · Checked 2026-09-05

external lighting shall be limited to downlighters
Remaining document questions
  • No final outfall selection, accepted connection, installed system or available contract is proven. Obtain the final drainage agreement; do not present the preferred option as selected.
  • Fitting brand, count, final approved photometry and installed light levels are not established. Inspect the illumination contour drawing and eventual appeal conditions.

One126-page NIS downloaded; document control and selected development, drainage and lighting pages visually inspected. Embedded appendices and whole council file are not fully reviewed.

Source history

Timeline

  1. Planning application received

    2660536

  2. Planning decision

    2660536

    Conditional permission

Evidence

Linked records

  • Commission case · 324591

    Case dates are not available in the current source coverage.

    Open official record

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.