Connected planning records

Planning case PCH0215

Dun Laoghaire Rathdown County Council · PCH0215 · Sallynoggin, Dublin

Latest linked evidence

Notified commencement · 2017-06-01

The development will consist of the demolition of the existing ramp to apartment block no.2 Rochestown House, and the construction of 1no. platform lift and 1no. external stairs. A temporary stairs will be constructed for use by residents for the extent of the construction programme, to be removed from site on completion of the new external stairs.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    PCH0215

  2. Planning decision

    PCH0215

    Decision recorded

  3. Notified commencement

    Commencement notice

    The development will consist of 14 no. new residential units consisting of 12 x 1 bed apartments and 2 x 2 bed bungalows, the demolition of the external ramp to existing block 1, and the construction of an external stairs to existing block 1.

    14 units stated for this notice or phase; not a project total.

    · Notice evidence

  4. Notified commencement

    Commencement notice

    The development will consist of the demolition of the existing ramp to apartment block no.2 Rochestown House, and the construction of 1no. platform lift and 1no. external stairs. A temporary stairs will be constructed for use by residents for the extent of the construction programme, to be removed from site on completion of the new external stairs.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.