Connected planning records

Planning case SD20A0283

South Dublin County Council · SD20A0283 · Clondalkin, Dublin

Latest linked evidence

Notified commencement · 2022-01-28

The DUB 14/15 110/20kV substation expansion area is a ‘design and build’ turnkey package, which is being delivered by Hitachi Energy and is separate from the rest of the site. The scope of works consists of the construction of a 110kV/20kV compound expansion which consists of 3 new 60MVA transformer bays and 3 new 20kv substations adjacent to the existing ESB/Eirgrid Corkagh 110kV Substation and the existing Microsoft transformer yard.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD20A0283

    Official source

  2. Planning decision

    SD20A0283

    Permission granted

    Official source

  3. Grant date recorded

    SD20A0283

    Official source

  4. Notified commencement

    Commencement notice

    Enabling works associated with Dub 14 & 15 consisting of the following : Bulk Earth Works , Excavations & Associated works , Fibre Works , Enabling , Demolition & External Carpark including toilets and bus stop.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Development of 2no. Data Buildings (DUB 14 & 15) substructure and super structural works in line with SD20A/0283 and enabling works for the Site Entrance/Bridge Construction; ie Modifications to external kerb lines / road alignment to create new entrance, Temporary haul road and working platform in river. All works in accordance with requirements of IFI and SDCC / Grangecastle Campus manager's requirements.

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    The DUB 14/15 110/20kV substation expansion area is a ‘design and build’ turnkey package, which is being delivered by Hitachi Energy and is separate from the rest of the site. The scope of works consists of the construction of a 110kV/20kV compound expansion which consists of 3 new 60MVA transformer bays and 3 new 20kv substations adjacent to the existing ESB/Eirgrid Corkagh 110kV Substation and the existing Microsoft transformer yard.

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    The DUB 14/15 110/20kV substation expansion area is a ‘design and build’ turnkey package, which is being delivered by Hitachi Energy and is separate from the rest of the site. The scope of works consists of the construction of a 110kV/20kV compound expansion which consists of 3 new 60MVA transformer bays and 3 new 20kv substations adjacent to the existing ESB/Eirgrid Corkagh 110kV Substation and the existing Microsoft transformer yard.

    Quantity not established for this notice.

    · Notice evidence

  8. Notified commencement

    Commencement notice

    The DUB 14/15 110/20kV substation expansion area is a ‘design and build’ turnkey package, which is being delivered by Hitachi Energy and is separate from the rest of the site. The scope of works consists of the construction of a 110kV/20kV compound expansion which consists of 3 new 60MVA transformer bays and 3 new 20kv substations adjacent to the existing ESB/Eirgrid Corkagh 110kV Substation and the existing Microsoft transformer yard.

    Quantity not established for this notice.

    · Notice evidence

  9. Notified commencement

    Commencement notice

    The DUB 14/15 110/20kV substation expansion area is a ‘design and build’ turnkey package, which is being delivered by Hitachi Energy and is separate from the rest of the site. The scope of works consists of the construction of a 110kV/20kV compound expansion which consists of 3 new 60MVA transformer bays and 3 new 20kv substations adjacent to the existing ESB/Eirgrid Corkagh 110kV Substation and the existing Microsoft transformer yard.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.