Connected planning records

Commercial new build, Marsh Road (to the east of Scotch Hall Shopping Centre)... - Planning Application 2560717

Louth County Council · 2560717 · Louth

Latest linked evidence

Planning decision · 2026-08-20

2560717 · Conditional permission

Current planning index: Further Information. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What is being built

Government document review

Council decision dated 20 August 2026, incorporating 3 July further information. A final grant and any later appeal outcome have not been established. Existing parking, the shopping centre and wider utility-study scope remain distinct.

3 official documents inspected · Checked 2026-09-06 · Official file index

The hotel decision is not a final grant

Council decision recorded; final grant and completed works unverified · Louth 2560717; hotel and its interfaces with the existing shopping centre

What the evidence says
The 20 August 2026 council decision describes a six-storey, 107-bedroom hotel, 54 reserved spaces in the existing shopping-centre car park and a first-floor bridge connection. July significant further information adds demolition works. The notification explicitly says the development is not authorised until the grant is made.

Louth 2560717; hotel and its interfaces with the existing shopping centre

Why it may matter — interpretation
Interpretation: keeps hotel rooms, existing reserved parking and the consent stage distinct.

What is not established
Any subsequent appeal, final grant and commencement are not established.

Inspect the evidence

Scotch Hall hotel: notification of decision · p.1
107 no. bedrooms · Issued 2026-08-20 · Seventeen conditions; incorporates 3 July significant further information; not a final grant · Checked 2026-09-06

107 no. bedrooms

Bridge acceptance carries detailed design conditions

Council decision recorded; final grant and completed works unverified · Hotel-to-shopping-centre pedestrian bridge, condition 8

What the evidence says
Condition 8 records a bridge floor depth of no more than 320 mm and 4.9 m clearance. Acceptance is conditional on further warning-signage details and structural-engineer assurance about collision resistance. These are the proposed bridge parameters and outstanding conditions, not verified built dimensions.

Hotel-to-shopping-centre pedestrian bridge, condition 8

Why it may matter — interpretation
Interpretation: shows the precise structural interface without treating conditional acceptance as completion.

What is not established
Final structural design, collision assessment, agreed signage and as-built clearance are unverified.

Inspect the evidence

Scotch Hall hotel: notification of decision · p.4
no more than 320mm · Issued 2026-08-20 · Seventeen conditions; incorporates 3 July significant further information; not a final grant · Checked 2026-09-06

no more than 320mm

Scotch Hall hotel: notification of decision · p.5
collision impacts · Issued 2026-08-20 · Seventeen conditions; incorporates 3 July significant further information; not a final grant · Checked 2026-09-06

collision impacts

The July drawing proposes a 2 L/s controlled outfall

Council decision recorded; final grant and completed works unverified · July further-information drainage route; existing outfall is not a new pipe quantity

What the evidence says
Revision A routes retained surface water through an attenuation manhole and hydrobrake at 2 L/s, across the car park to the existing quay-wall outfall. The drawing labels that existing outfall 300 mm. The applicant’s assertion that discharge rights need no alteration is not treated as independent approval of those rights; final permissions and flood interfaces remain separate.

July further-information drainage route; existing outfall is not a new pipe quantity

Why it may matter — interpretation
Interpretation: connects the proposed hotel drainage to its stated destination and separates design from permission.

What is not established
Final discharge consent, hydraulic verification, tank capacity and installed route are unverified.

Inspect the evidence

Scotch Hall hotel: proposed surface-water drainage · p.1
a hydrobrake limiting flow to 2l/s · Issued 2026-06-26 · SERV.02 Revision A; further-information response drawing received 3 July · Checked 2026-09-06

a hydrobrake limiting flow to 2l/s

The shared utility feasibility letter is not a connection agreement

Council decision recorded; final grant and completed works unverified · Shared feasibility correspondence versus this hotel application

What the evidence says
The July response includes Uisce Éireann correspondence saying the earlier mixed-use feasibility scope includes one hotel. It also includes separate residential and retail uses, which are not added to this hotel’s scope. August condition 5 still requires valid feasibility or design-acceptance evidence for the hotel before commencement.

Shared feasibility correspondence versus this hotel application

Why it may matter — interpretation
Interpretation: avoids mistaking a wider service study for additional hotel development or a completed connection.

What is not established
The final hotel-specific design acceptance, connection agreement and installed services are unverified.

Inspect the evidence

Scotch Hall hotel: further-information response · p.4
included for this hotel · Issued 2026-07-02 · Received 3 July; includes applicant drainage assertions and separate utility correspondence · Checked 2026-09-06

included for this hotel

Scotch Hall hotel: notification of decision · p.4
Statement of Design Acceptance · Issued 2026-08-20 · Seventeen conditions; incorporates 3 July significant further information; not a final grant · Checked 2026-09-06

Statement of Design Acceptance

The junction still needs civil and electrical detail

Council decision recorded; final grant and completed works unverified · Condition 7; proposed junction serving the hotel

What the evidence says
Condition 7 requires refinement of the new signalised Marsh Road/New Street junction, including adjusted stop lines and detailed civil, mechanical-and-electrical and phasing drawings. This is a defined highway interface requiring agreement; the decision does not specify a signal-equipment supplier.

Condition 7; proposed junction serving the hotel

Why it may matter — interpretation
Interpretation: identifies the transport engineering package and its remaining approval step.

What is not established
Agreed junction drawings, signal products and completed works are unverified.

Inspect the evidence

Scotch Hall hotel: notification of decision · p.4
civil, M&E and phasing drawings · Issued 2026-08-20 · Seventeen conditions; incorporates 3 July significant further information; not a final grant · Checked 2026-09-06

civil, M&E and phasing drawings
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 3 government-published PDFs were visually inspected. 70 index rows retained; selected pages of three supporting PDFs visually inspected. This is not an exhaustive review of all architectural, traffic, ecological or later compliance material. Proposals do not establish procurement or installed work.

Source history

Timeline

  1. Planning application received

    2560717

  2. Planning decision

    2560717

    Conditional permission

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.