Planning case 22993

Kildare County Council · 22993 · Kilcullen, Kildare

Latest linked evidence

Notified commencement · 2026-08-26

The development consists of the phased demolition of existing school buildings, with the exception of the former convent and nearby stone building which are to be retained and refurbished, and the construction of a new two and three-storey school extension of approximately 10,375m² incorporating 37 general classrooms, support and specialist classrooms, a Special Educational Needs unit, a library, multimedia rooms, a single-storey multi-use sports hall, staff rooms, including photovoltaic panels. The development also includes the erection of temporary school accommodation units to allow the school to remain operational during construction, material alterations to retained buildings, a new ESB substation, and associated site works including car and bicycle parking, hard and soft landscaping, the retention of existing sports pitches and trees, drainage infrastructure, and all other ancillary site development works at Cross and Passion College, Main Street, Kilcullen, Co. Kildare,.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    22993

  2. Planning decision

    22993

    Conditional permission

  3. Grant date recorded

    22993

  4. Notified commencement

    Commencement notice

    The development consists of the phased demolition of existing school buildings, with the exception of the former convent and nearby stone building which are to be retained and refurbished, and the construction of a new two and three-storey school extension of approximately 10,375m² incorporating 37 general classrooms, support and specialist classrooms, a Special Educational Needs unit, a library, multimedia rooms, a single-storey multi-use sports hall, staff rooms, including photovoltaic panels. The development also includes the erection of temporary school accommodation units to allow the school to remain operational during construction, material alterations to retained buildings, a new ESB substation, and associated site works including car and bicycle parking, hard and soft landscaping, the retention of existing sports pitches and trees, drainage infrastructure, and all other ancillary site development works at Cross and Passion College, Main Street, Kilcullen, Co. Kildare, .

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.