Commencement notice group
Building extension commencement notices — Kilcullen
Kilcullen, Kildare
1 unique commencement event · latest notified commencement 26 Aug 2026 · planning reference supplied
- Unique commencement events
- 1
- Latest notified commencement
- 26 Aug 2026
- Latest notice
- 45,671 m²
- Planning references supplied
- 22/993
- Public location
- Kilcullen, Kildare
Verified project chain
Planning, start and completion evidence
- Exact planning records
- 1
- Official record actions
- 1
- Explicit planning relationships
- 0
- Duplicate source rows consolidated
- 1
- Exact completion events
- 0
- Open exact official planning record: 22/993 Kildare County Council
Planning, commencement and completion remain separate exact-source events. Completion certificates are shown only after the official planning, commencement, certificate and PDF evidence chain passes; notice quantities are never added into a project total.
Planning-anchored public geography
Site identity and location
- Canonical public locality
- Kilcullen, Kildare
- County
- Kildare
- Approximate commencement source point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
The exact official planning file is available below.
-
Official planning file Kildare County Council planning record Application details, status and decision record for 22/993. Official council planning portal Official link · not recently checked Exact normalized planning authority and local planning reference in the indexed official planning record.Open official planning file · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
The development consists of the phased demolition of existing school buildings, with the exception of the former convent and nearby stone building which are to be retained and refurbished, and the construction of a new two and three-storey school extension of approximately 10,375m² incorporating 37 general classrooms, support and specialist classrooms, a Special Educational Needs unit, a library, multimedia rooms, a single-storey multi-use sports hall, staff rooms, including photovoltaic panels. The development also includes the erection of temporary school accommodation units to allow the school to remain operational during construction, material alterations to retained buildings, a new ESB substation, and associated site works including car and bicycle parking, hard and soft landscaping, the retention of existing sports pitches and trees, drainage infrastructure, and all other ancillary site development works at Cross and Passion College, Main Street, Kilcullen, Co. Kildare, .
Floor area stated for this source: 45,671 m².
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.