Infrastructure · Co. Cork
Mallow Business & Technology Park Quartertown Lower Mallow, Co. Cork
Granted 23 Jul 2015 (final grant issued 28 Aug 2015)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 15/4690 at Mallow Business & Technology Park Quartertown Lower Mallow, Co. Cork: New fabricating workshop with attached two-storey office block…
- It was received by Cork County Council on 8 Apr 2015.
- Status: Granted 23 Jul 2015 (final grant issued 28 Aug 2015).
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 23 Jul 2015.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New fabricating workshop with attached two-storey office block…
Construction of (1) new fabricating workshop (3200 m²) with attached two-storey office block and canteen area (1028 m²), (2) single storey ESB substation, (3) single storey stainless steel cleaning building, (4) 5X5m overground rainwater storage tank, and (5) all ancillary site works including on-site car park
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 15/4690
Numbers and dates
- Floor area
- 4,228 m²
- Project type
- Infrastructure
- Received
- 8 Apr 2015
- Decision to grant
- 23 Jul 2015
- Final grant
- 28 Aug 2015
- Site start notified
- 4 Jan 2016
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 15/4690.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 4 Jan 2016Notice filed · The construction of a new fabrication workshop with attached two-storey office and...View the site start
- Completion certificate recordedRecorded in Jan 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.