Infrastructure · Co. Cork

Strand Street Kanturk Co. Cork

Granted 21 Jul 2017 (final grant issued 29 Aug 2017)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 16/7019 at Strand Street Kanturk Co. Cork: Extension and improvements to site boundary in the form of a new…
  • It was received by Cork County Council on 5 Dec 2016.
  • Status: Granted 21 Jul 2017 (final grant issued 29 Aug 2017).
  • Work was due to start on 20 Jun 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 12 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 21 Jul 2017.

Application details as we last saw them in the national register on 12 Jun 2026.

What and where

Extension and improvements to site boundary in the form of a new…

Construction of extension and improvements to site boundary in the form of a new footpath and removable bollards. The building extension will serve as an extension to cold storage facilities and as an improved facility for product dispatch operations. The new extension will cover the existing office block building and will hide dispatch operations from the public eye. The building extension and associated works will comprise of (1) a new loading dock building with four roller shutter doors and staff access door via external stairs (2) one low level retaining wall with protection rail, (3) a new concrete paved open yard with declining ramp from footpath to building, (4) two kerbs alongside declining ramps, (5) a new pedestrian footpath at road interface, (6) removable bollards between footpath and yard, (7) one petrol interceptor for surface water cleansing and (8) all associated site works. A Natura Impact Statement will be submitted to the Planning Authority with the application.

Location
Co. Cork Map
Planning reference
16/7019

Numbers and dates

Project type
Infrastructure
Received
5 Dec 2016
Decision to grant
21 Jul 2017
Final grant
29 Aug 2017
Site start notified
20 Jun 2018

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 20 Jun 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 16/7019.Search the register

How we know this

From the Cork County Council planning register, as last seen on 12 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 20 Jun 2018Notice filed · Construction of an extension to North Cork Creameries existing facility at Strand Street...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options