Works to connect the permitted Boolard Wind Farm, Charleville, Co. Cork
Granted on appeal 4 Feb 2019 (Decision to grant 26 Jan 2018 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Charleville by email
Key facts
- Planning application 17/5292 at Charleville, Co. Cork: Works to connect the permitted Boolard Wind Farm.
- It was received by Cork County Council on 24 May 2017.
- Status: Granted on appeal 4 Feb 2019 (Decision to grant 26 Jan 2018 by the council).
- Work was due to start on 24 Apr 2019, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Charleville · Planning applications in Co. Cork
Council register
The council's register shows: Decision to grant on 26 Jan 2018.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Works to connect the permitted Boolard Wind Farm
Works to connect the permitted Boolard Wind Farm (Reg. Refs. 12/5997 and 15/5521/PL.04.245560) to the existing Charleville 110kv ESBN substation comprising as follows: installation of approximately 5.694 km of 20kv underground electricity cable and fibre communications cable in ducting; 12 no. joint bays, 12 no. communications chambers and 2 no. earth link boxes (all underground); access covers to chambers and boxes at finished surface level; ancillary marker posts and marker plates as necessary; the replacement of an existing concrete pipe with a box culvert under an existing agricultural track and the construction of new parapet walls above the track; and all associated site development and reinstatement works. The development will consist of alterations to permitted wind farm site layout (as per Reg. Ref. 12/5997 and 15/5521 / PL.04.245560) as follows i) widening of permitted vehicular site entrance, ii) provision of 2 no. turning areas/overrun areas for turbine delivery/construction vehicles off the permitted wind farm site road iii) localized realignment and refinement of internal wind farm site road network, iv) increased crane pad size at both permitted turbine locations, and v) also, construction of control building (minor change of location from Reg. Ref. 15/5521/PL.04.245560).
- Location
- Charleville, Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 17/5292
Numbers and dates
- Project type
- Infrastructure
- Received
- 24 May 2017
- Council decision
- 26 Jan 2018
- Appeal lodged
- 22 Feb 2018
- Granted on appeal
- 4 Feb 2019
- Site start notified
- 24 Apr 2019
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Site history
This site's history
-
Earlier permission 12/5997 for this site: granted 9 Nov 2012.
Construction of 2no. wind turbines with tip height up to 150.5m, control building, 100m wind monitoring mast and associated site works… Named in this application's description -
Earlier permission 15/5521 for this site: decision to grant 3 Sep 2015.
Construction of control building for wind turbine development (change of plan from that permitted under planning reg. No. 12/5997) to meet… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 17/5292.Search the register
- AppealGrant permission with revised conditions · 301000 / 4 Feb 2019View the appeal record
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 24 Apr 2019Notice filed · Construction of substation to service wind farm at Boolard, Co. Cork.View the site start