Infrastructure · Co. Cork
Alteration of Mallow Sewerage Scheme to remove combined sewer…, Kilknockan, Co. Cork
Granted 4 Dec 2019 (final grant issued 13 Jan 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 19/5078 at Kilknockan, Co. Cork: Alteration of Mallow Sewerage Scheme to remove combined sewer…
- It was received by Cork County Council on 30 Apr 2019.
- Status: Granted 4 Dec 2019 (final grant issued 13 Jan 2020).
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 4 Dec 2019.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Alteration of Mallow Sewerage Scheme to remove combined sewer…
The alteration of Mallow Sewerage Scheme to remove combined sewer overflows from the network. The proposed scheme will include: 1. The alteration of Mallow Wastewater Treatment Plant to provide for wastewater treatment capacity for 22,000pe (increased from 18,000pe) at Ballyellis, Mallow. The WWTP upgrade will comprise construction of new local pumping station, refurbishment/replacement of inlet works, distribution chambers, alteration of existing tanks, construction of plinths and kiosks, sludge import acceptance unit, sludge tanks, chemical storage tanks, associated pumps, replacement of sludge presses in existing sludge building with centrifuges, all with associated odour control facilities, electrical control panels and kiosks, standby power generation equipment and diesel tank, extensions to existing access roads and all associated site development and site excavation works above and below ground. 2. Construction of a new pump station at Bearforest Lower, Mallow, to transfer flows from the network to the WWTP at Ballyellis. The development will contain a foul sump, storm sump, valve chamber, lifting gantries, access stairs, control house with MV Substation, storm tank, interconnecting pipework and chambers, overflow pipework and chambers from storm tank to river Blackwater, twin rising mains to WWTP at Ballyellis, flow meter chambers, odour control equipment, 2.4m high boundary fence, access gate, access roads, hardstanding areas, landscaping and all associated site development and site excavation works above and below ground. Existing pump station to be decommissioned and above ground structure demolished on completion. 3. Upgrade of sections of the sewer network in Mallow comprising construction of pipelines and chambers in fields, public open spaces, roads and footpaths in the townlands of Ballyellis, Bearforest Lower, Ballydahin, Carhookeal, Quartertown Lower, Castlelands, Mallow, Annabella, Lackanalooha, Kilknockan and Spa Glen. Pipelines will include a crossing of the river Blackwater between Castlelands and Bearforest Lower east of Mallow Bridge. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with this application.
- Location
- Kilknockan, Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 19/5078
Numbers and dates
- Project type
- Infrastructure
- Received
- 30 Apr 2019
- Decision to grant
- 4 Dec 2019
- Final grant
- 13 Jan 2020
- Site start notified
- 16 Mar 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 19/5078.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 16 Mar 2022Notice filed · Construction of sewerage treatment plant control building, including substation, switch...View the site start
- Completion certificate recordedRecorded in Mar 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.